Help, % complete doesn't reflect reality

Member for

18 years 2 months

James,

 

You have to make a custom formula for the % complete you wish, in your case manhours. You won't be using anymore the Duration % Complete. Apply this formula in the custom field and add it as a column.

Hope this helps.

 

Chris

Member for

19 years 1 month

yes of course there are differences in calculating % progress;

if you want to use duration as your factor, then you have to tailor your plan to be adaptable to duration;

otherwise, you can either use resource units and/or cost;

or maybe your own weighting factor;

the software will never tell you what is the right weight factor to use;

you need to find it out yourself,

by the way, I've never seen yet if MSP calculates planned % progress (or based on what factor?).

Member for

13 years 2 months

No, that doesn't work, i can't get anymore detailed than I have. I have more than 1000 lines. Unless I break it down into what they do every hour which isn't feasible.

I'll give you a simplified example of the problem:

It takes 10 men 10 days to perform the first task.

It takes 1 man 10 days to perform the second task.

The first task is 100% complete, the second task is 0%. The completion should be 91%, however MS Project says it is 50% (impossible) - it is just calculating from duration (10 days and 10 days) and not taking into account the hours it takes to do it.

Member for

20 years 1 month

There must be other pecentage complete types in MS Poject 2003. I have not used MSP as such can not be specific.

It looks you are using Duration percentage complete (OD-RD)/OD.

In P6 this situation can be handled by performace, units or physical pecentage complete.

 

Regards

Shareef A Azeez

 

Member for

19 years 1 month

that's what I'm trying to say,

if you are able to decompose your tasks into a daily duration, then you will get rid of longer duration for a single resource;

then I guess that you will get what you need.

Member for

13 years 2 months

I have very detailed tasks and the majority are 100% complete. But I have several tasks lasting many days (for 1 man) which make the duration seem longer in total than the tasks that have been completed. Perhaps there is some settings that need to be altered?

Member for

19 years 1 month

I suggest you decompose your task (or activities) to as much details as you can;

the more you got details the more it will become accurate;

if you got details to the minute, then you can allocate your resources (or man-hours) accurately (or maybe nearly).