Reply of Client for my EOT Claim

Member for

13 years 11 months

Dear Shareef Abdul Azeez

 

Thank you for your kind reply.Can you please explain that how it will be shown in activity usage spreadsheet.The said schedule is not loaded with manhours or man-months.And what doest High activity and low activity means?? Does it mean the predecessor and successor?

 

Regards

Member for

20 years 1 month

Hello

 

If you use an activity usage spread sheet the low activity and high activity usage months can be assertained. 

 

Member for

13 years 11 months

I am confused about this line: 

Please send me a break-up of the above extension period based on construction activity i.e. dormant months, low activity and high construction activity so I can try for some reduction of premium at least for the dormant months.

 

I do not understand the Low activity and high activity.what are these that he is referring to?

 

Regards