Cumulative late curve

Member for

15 years

Hi Wynand,

Thx for this info..

Sunil.

Member for

19 years 10 months

Hi Wynand

Why not just add the day total float to the ASAP date.

Best regards

Mike Testro

Member for

14 years 10 months

I will put a finish as late as possible constraint on all the the task export the timescale data to excel , that is how i do it in Microsoft Projects 2010, not to sure how in P6 , hope it helps.