Planning, Scheduling & Programming Discussion Member for 15 years Member for 15 years Submitted by sb_sunil2000 on Tue, 2012-06-19 12:34 Permalink Hi Wynand, Thx for this Hi Wynand, Thx for this info.. Sunil. Member for 15 years Member for 15 years Submitted by sb_sunil2000 on Tue, 2012-06-19 12:32 Permalink Hi Mike, Thx for this info... Hi Mike, Thx for this info... Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2012-06-19 10:01 Permalink Hi Wynand Why not just add Hi Wynand Why not just add the day total float to the ASAP date. Best regards Mike Testro Member for 14 years 10 months Member for 14 years 10 months Submitted by wy****@o***** on Tue, 2012-06-19 08:50 Permalink I will put a finish as late I will put a finish as late as possible constraint on all the the task export the timescale data to excel , that is how i do it in Microsoft Projects 2010, not to sure how in P6 , hope it helps. Log in or register to post comments
Member for 15 years Member for 15 years Submitted by sb_sunil2000 on Tue, 2012-06-19 12:34 Permalink Hi Wynand, Thx for this Hi Wynand, Thx for this info.. Sunil.
Member for 15 years Member for 15 years Submitted by sb_sunil2000 on Tue, 2012-06-19 12:32 Permalink Hi Mike, Thx for this info... Hi Mike, Thx for this info...
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Tue, 2012-06-19 10:01 Permalink Hi Wynand Why not just add Hi Wynand Why not just add the day total float to the ASAP date. Best regards Mike Testro
Member for 14 years 10 months Member for 14 years 10 months Submitted by wy****@o***** on Tue, 2012-06-19 08:50 Permalink I will put a finish as late I will put a finish as late as possible constraint on all the the task export the timescale data to excel , that is how i do it in Microsoft Projects 2010, not to sure how in P6 , hope it helps.
Member for
15 yearsHi Wynand, Thx for this
Hi Wynand,
Thx for this info..
Sunil.
Member for
15 yearsHi Mike, Thx for this info...
Hi Mike,
Thx for this info...
Member for
19 years 10 monthsHi Wynand Why not just add
Hi Wynand
Why not just add the day total float to the ASAP date.
Best regards
Mike Testro
Member for
14 years 10 monthsI will put a finish as late
I will put a finish as late as possible constraint on all the the task export the timescale data to excel , that is how i do it in Microsoft Projects 2010, not to sure how in P6 , hope it helps.