Thanks for the pointers, Mike. My school only has MS Project, but I think I'll be able to use excel to make a one resource spreadsheet under "Hours," and then punch in the values, but I'll have to figure out how to incorporate that into my msp programme.
I think I got better understanding of landscaping, I'll fiddle with my programme and try to graft a 3-phase landscape sequence into my plan. The new trade issue is a interesting point, I would have never thought of that, I think maybe I can get something added into the custom field tabs on Msproject to start a new sub on Monday.
Appreciate the feedback, I'll try more coffee first, but I may bug you again if I get stuck and start to develop the urge to shoot myself.
1. Roads and hardstanings up to formation for access routes and site establishment.
2. Work close in to the structure when the scaffold is down.
3. Planting and soft work towards the end of the project.
Using price books is a good way to establish resource outputs for resource modelling.
You will make your life much easier by using only one resource called "Hours" and setting up a spreadsheet for each task with a column for each of:
1. Volume of Work
2. Output
3. Gang size
These can then be added to the resource modelling software.
If you are using software such as Powerproject the numbers can be copy / pasted directly into the programme columns and the result will be instant.
With other types of software you will have to type them all in.
One benefit of this type of resource modelling is that when the volume of work changes the effect on the programme will be instantaneous.
Another thing to remember on the practical side of things is that the modelled durations will not be a full day so if one trade ends at 15:30 on Tuesday the programme assumes that the next trade will pile in that afternoon to do 1.5 hours work.
That just does not happen.
Some software allows you to set the next trade to start on the following day others don't - in which case you have to round up your spreadsheet numbers to fix a full day duration - this is best done by adding a balancing column next to the calculated hours so that it rounds up to your work pattern.
Another fact of life to remember is that no new subbie will ever start on a Wednesday morning - "We'll be there on Monday" is the normal mantra.
There is a way of fixing this so that every new trade starts on a Monday morning - I will leave you to figure it out.
After a few more nights of trying to figure out the planning of this building, I think I'm closer to the end.
Thanks for taking the time to look at it, Mike.
I reviewed your suggestions and tried to incorporate them into the plan. I couldn't get my boarding of L1 to time coincidentally with the approximate time of L1 weather-tightness; however, maybe I can figure out how to sequence the MEP rough-in to be more efficient, as well as my interior finishes cycle. I'm not quite sure when the landscape and hardscape could go, on my next edit I will presume it is ok to commence once all the dry wall is loaded or when all the cladding/painting is done so there is are no longer any booms/jibs/scissors in the way.
This is what it looks like now (MS Project 2010 I can convert it if need be) I'd appreciate any feedback/constructive criticism.
On a side note, I'm thinking about buying some man-hour estimation books so I can learn to calculate duration a little more accurately as right now i'm just somewhat ''guesstimating." My school uses RSMeans Con. Cost Data, is this what you guys use, or is there something else more efficient for estimating durations. RSMeans seems to be exhaustive to the point where you have to review every component down to the type of screw used...
I have just had a quick look at your programme and in my opinion you are on the right track.
You use FS links which is good practice but you should not use any sort of lead lags except for your curing periods that can best be set by Lead Lag links using - as you have done - Elapsed days. This makes progress reporting easier as you do not have to estimate a percentage of days.
I could not find any link between weather tight conditions and internal finishings.
You have a link from 146 to 294 when there should be a weather tight milestone that links FS to your first weather sensitive finishings. This would seem to be 172.
There are a number of open ended tasks - every task must have at least 1 succesor unless it is the last one.
Member for
13 years 5 monthsThanks for the pointers,
Thanks for the pointers, Mike. My school only has MS Project, but I think I'll be able to use excel to make a one resource spreadsheet under "Hours," and then punch in the values, but I'll have to figure out how to incorporate that into my msp programme.
I think I got better understanding of landscaping, I'll fiddle with my programme and try to graft a 3-phase landscape sequence into my plan. The new trade issue is a interesting point, I would have never thought of that, I think maybe I can get something added into the custom field tabs on Msproject to start a new sub on Monday.
Appreciate the feedback, I'll try more coffee first, but I may bug you again if I get stuck and start to develop the urge to shoot myself.
Matthew
Member for
19 years 10 monthsHi Matthew Landscaping is
Hi Matthew
Landscaping is often in three stages.
1. Roads and hardstanings up to formation for access routes and site establishment.
2. Work close in to the structure when the scaffold is down.
3. Planting and soft work towards the end of the project.
Using price books is a good way to establish resource outputs for resource modelling.
You will make your life much easier by using only one resource called "Hours" and setting up a spreadsheet for each task with a column for each of:
1. Volume of Work
2. Output
3. Gang size
These can then be added to the resource modelling software.
If you are using software such as Powerproject the numbers can be copy / pasted directly into the programme columns and the result will be instant.
With other types of software you will have to type them all in.
One benefit of this type of resource modelling is that when the volume of work changes the effect on the programme will be instantaneous.
Another thing to remember on the practical side of things is that the modelled durations will not be a full day so if one trade ends at 15:30 on Tuesday the programme assumes that the next trade will pile in that afternoon to do 1.5 hours work.
That just does not happen.
Some software allows you to set the next trade to start on the following day others don't - in which case you have to round up your spreadsheet numbers to fix a full day duration - this is best done by adding a balancing column next to the calculated hours so that it rounds up to your work pattern.
Another fact of life to remember is that no new subbie will ever start on a Wednesday morning - "We'll be there on Monday" is the normal mantra.
There is a way of fixing this so that every new trade starts on a Monday morning - I will leave you to figure it out.
Best regards
Mike Testro
Member for
13 years 5 monthsBah,After a few more nights
Bah,
After a few more nights of trying to figure out the planning of this building, I think I'm closer to the end.
Thanks for taking the time to look at it, Mike.
I reviewed your suggestions and tried to incorporate them into the plan. I couldn't get my boarding of L1 to time coincidentally with the approximate time of L1 weather-tightness; however, maybe I can figure out how to sequence the MEP rough-in to be more efficient, as well as my interior finishes cycle. I'm not quite sure when the landscape and hardscape could go, on my next edit I will presume it is ok to commence once all the dry wall is loaded or when all the cladding/painting is done so there is are no longer any booms/jibs/scissors in the way.
This is what it looks like now (MS Project 2010 I can convert it if need be) I'd appreciate any feedback/constructive criticism.
https://docs.google.com/open?id=0B1UCST5kO3r2T0Fid1kwaHVMTlU
On a side note, I'm thinking about buying some man-hour estimation books so I can learn to calculate duration a little more accurately as right now i'm just somewhat ''guesstimating." My school uses RSMeans Con. Cost Data, is this what you guys use, or is there something else more efficient for estimating durations. RSMeans seems to be exhaustive to the point where you have to review every component down to the type of screw used...
Much thanks,
Matthew
Member for
19 years 10 monthsHi Matthew I have just had a
Hi Matthew
I have just had a quick look at your programme and in my opinion you are on the right track.
You use FS links which is good practice but you should not use any sort of lead lags except for your curing periods that can best be set by Lead Lag links using - as you have done - Elapsed days. This makes progress reporting easier as you do not have to estimate a percentage of days.
I could not find any link between weather tight conditions and internal finishings.
You have a link from 146 to 294 when there should be a weather tight milestone that links FS to your first weather sensitive finishings. This would seem to be 172.
There are a number of open ended tasks - every task must have at least 1 succesor unless it is the last one.
Let us see what other members have to say.
Good luck in your new career.
Best regards
Mike Testro