Using hours as the unit measure of work is misleading, is wrong, is absurd.

Member for

19 years 10 months

Hi Rafael

I use a single resource for duration modelling which I call hours.

This resource is extracted from the labour content in the cost plan so the time - cost - scope triangle is balanced.

Best regards

Mike Testro

BTW you are rapidly catching up on me - I must get some more threads in.

Member for

16 years 11 months

Hi to all and Many thanks to Mr.Rafael 

I had a doubt of similar issue and got cleared by Mr.Rafel.I have even raised this issue to MS Project Expert Forum they came with the answer 

 

""It doesn't :-(

In Project Work is measured based on time worked,not on physical quantities.

There is the possibility to enter a value called Physical Percent Complete (which can be used in earned value calculations) but if you want to use it you have to enter it yourself, Project does not calculate it.""

 

Regards

Shahul

Member for

21 years 8 months

Anoon,

F=ma = mass x acceleration

Acceleration = dv/dt = change of velocity over time

Velocity = dx/dt = change of location over time

Time is of utmost importance when you define work, but work per se is not time.

Of course the appropriate definition depends on the use of the concept. For accounting purposes work is measured in hours no matter if there is an output or not. For the Construction Industry as a whole, work is measured in physical units as Vladimir pointed out.

MS Project as well as P6, originally P3e are software developed by IT people, people who never accounted nor cared for how the construction industry defines work, perhaps followed the thinking of accountants who measure work by pay hour no matter what the employee produced. Primavera even issued a version of P3e called P3ec, P3 for people to relate it to P3 a product developed by other people, e to mean enterprise and c to mean construction, this marketing strategy was later abandoned.

In the Construction Industry we do not say an hour of effort by a 1cm backhoe yields the same work as an hour of effort a 2cm backhoe will yield.  Still in our industry, time is of utmost importance with regard to work. We relate the time element to work with the concept of productivity.

Work = Physical Quantity = Sum of (Productivity x time)

Time = effort

Productivity = Physical Quantity/effort = Physical Quantity/ time

MS Project as well as P6 was never designed taking into account the language and the concepts used by many generations in the Construction Industry. They pretend the whole industry to adapt to their concept, but their concept is inappropriate  for the purposes of a whole industry. Their problem is that in order to accommodate their software to the appropriate concept of work for the Construction Industry they would have to resort into major surgery in their software and even start from scratch.

Best regards,

Rafael

Member for

24 years 9 months

In construction we usually measure the work and the progress in physical units like 25m3 of 40m3 were already done.

Member for

19 years 1 month

Hi Rafael,

Work - they said Work = force multiplied by distance (W= F x D), so it doesn't involved time.

Let me ask you, what do you mean by Progress?

 

cheers

Member for

14 years 7 months

Evry measure for progress is a simulation.Planner should choose  different measure for different situation.

For example, to the  design or construction work,  manhour is one of the most suitable measures ,but to the procurement maybe milestone.

And ,to  the productivity, different contractor have different equipment and worker. the productivity gap is huge. 

So,your plan and manhour assigned to the work  should match the contractor and in accordance with your contract strategy. Overall, manhours can not solve all the problem ,but it is a good simulation to the progress measure.

(Sorry for the expresstion, i am just a half year english learner)

Member for

17 years 11 months

Rafael,

What should be correct method to measure progress if not hours?

Please explain.

 

Thanks

SE Ali