The norm; for 40+ storys, on removing of RC. Slab back propes you start working on first; svp & rvp then external envelops Glazing as a means of wp the bldg, or in pararell internal partition frames only,
hI, GUYS CAN ANYONE PL PROVIDE ME WITH THE SAMPLE HIGH RISE SCHEDULE INCLUDING CIVIL+FINISHES+MEP+CLADDING MENTIONING THE CONSIDERATIONS THAT ARE BEING ADOPTED IN...ASAP.
REGARDS.
Member for
19 years 2 months
Member for19 years3 months
Submitted by Santhosh kumar… on Thu, 2010-10-07 13:17
Yeah it maily depends the hieght of building and your contract completion date (finish date) as mentioned above you can start block work, plaster etc (wet works) immediately after removal of form, provide 2-3 days lag for cleaning & preparation
Externak cladding, in your case, can start after 20 floors ( devide the entire floors in to 3 sections) once extranal cladd in palce and site is temaparly water proofed you can proceed with MEP Services 1st & second fix and other dry works.
Final fix and final paints at the end after the total tower become water tight.
In general if you consider 7 days cycle from typical floor (Say from GF) you can start cladding after 140 + 14 days. (14 days is curing period and protection around against fallling opbect form upperfloors.
Member for
24 years
Member for24 years1 month
Submitted by Daniel Limson on Wed, 2010-10-06 06:12
There are several things you need to consider before you start interior finishes, the wet trades, block walls and plastering can start as soon as you removed your temporary support (Props), If you have drywall (gypsum boards), the Building has to be watertight, meaning your curtain wall is already in place on that floor and watertighness or temorary waterproofing measures have been implemented up to a certain level of the building (say in your case the first 15 floors). Joneries requires good weather conditions to start (enviromentally controlled if possible). Extreme weather conditions like the Middle East requires temporary air conditioining before they start any joineries.
The Curtain wall or the cladding of a building can start, if you have adequate safety measures in place, like a catch pan to protect workers from falling objects. They normally require the structure completed up 15 to 20 storey before they start.
THe building services, HVAC, FS, Water, Drainage, etc. Normallly will start from the risers (Main lines) first and then branches out or tee off to each level but it can also be done the other way around.
Note that all your building services should be in place and tested before you close the ceiling.
Some projects use a temporary membrane to allow finishes to proceed due to the risk mentioned earlier about rain running through penetrations, stairways, etc. Remember that you also need to store your materials on a watertight floor/s.
the interior architectural works of a high rise building has two major division, the wet works(eg. chb & finishes, waterproofing, skimcoating) and the dry works(eg. gypsum wall & ceiling, carpets,fixtures).
The wet works can start as soon as the scaffolds & shorings at the ground level has been removed, this will depend on structural specifications and the curing period of the concrete used. however, the start of wet works is usually deffered depending on the available time and the manner of hand over required by the client.
The dry works usally start when the building is already "partially watertight", this milestone date comes when half of the buildings perimeter glass/glazing is already installed. this consideration vary depending on the height of the building.In your case, you may take the 30th floor glass/glazing installation as the predeccesor of partial watertightness.
Please give me some information about the type of building (Residential/Commercial?)and scope of work (Shell & Core/Fit out?). Do not forget to include some information about the cladding and its method of installation.
Internal Finishes will need protection from external weather conditions - particularly rain & wind. The cladding will only protect you partly until the whole of the Envelope is complete. Service holes, slab perimeter, and stair cores will be of main concern in regards to water ingress.
Maybe you could specify further, are you talking about the architectural works like start of CHB works or it is really what Larry is recommending which is finishing works?
Larry, thanks for the milestone and the logic as well...
You need to look at it from a logical sequence of works. After the frame, you have the vertical cladding to consider. Start of Internal Finishes will depend on the cladding progression and temporary waterproofing measures. I would recommend that you insert a milestone ‘building sufficiently waterproofed to start Internal Finishes’.
Also consider the installation rate of cladding Vs Fit-Out - as Internal Finishes is not to surpass cladding.
Regards,
Larry
Member for
22 years 5 months
Member for22 years5 months
Submitted by Christian Adri… on Fri, 2006-09-29 01:16
I would consider the readiness of the area and the number of people, equipment, and materials available at site... you dont want your project to get to crowded...
Member for
19 years 10 months
Member for19 years11 months
Submitted by Armando Moriles on Fri, 2006-09-29 00:09
I would suggest for you to have a check first at the construction dead and live loads being considered in the structual design. They might dictate the restrictions.
Member for
15 years 1 monthThe norm; for 40+ storys, on
The norm; for 40+ storys, on removing of RC. Slab back propes you start working on first; svp & rvp then external envelops Glazing as a means of wp the bldg, or in pararell internal partition frames only,
Member for
10 yearsDear all,want any one to
Dear all,
want any one to guide me for book describe in detail of logic sequence for construction activities
also the durations
Member for
11 years 11 monthsdear all could u send me a
dear all
could u send me a copy of high raise building project on primavera 6 to take an idea about activities and its sequence
that will help me in my work
plz any one have it send it to me my email: mohamedezat78@hotmail.com
thanks
eng:mohamed ezat
Member for
13 years 8 monthsFloor InstallationThe blog
Floor Installation
The blog post is so good and providing a lot of information about healthcare and medical knowledge, everyone should go for this website.
Member for
19 years 10 monthsHi Raja Welcome to Planning
Hi Raja
Welcome to Planning Planet.
A few rules on PP etiquette
1. Do not wake up long dead threads - start a new topic.
2. Do mot use capitals in the body of your text - its the equivalent of shouting
3. Only press the save buttone once.
Best regards
Mike Testro
Member for
15 years 7 monthshI, GUYS CAN ANYONE PL
hI, GUYS CAN ANYONE PL PROVIDE ME WITH THE SAMPLE HIGH RISE SCHEDULE INCLUDING CIVIL+FINISHES+MEP+CLADDING MENTIONING THE CONSIDERATIONS THAT ARE BEING ADOPTED IN...ASAP.
REGARDS.
Member for
19 years 2 monthsYeah it maily depends the
Yeah it maily depends the hieght of building and your contract completion date (finish date) as mentioned above you can start block work, plaster etc (wet works) immediately after removal of form, provide 2-3 days lag for cleaning & preparation
Externak cladding, in your case, can start after 20 floors ( devide the entire floors in to 3 sections) once extranal cladd in palce and site is temaparly water proofed you can proceed with MEP Services 1st & second fix and other dry works.
Final fix and final paints at the end after the total tower become water tight.
In general if you consider 7 days cycle from typical floor (Say from GF) you can start cladding after 140 + 14 days. (14 days is curing period and protection around against fallling opbect form upperfloors.
Member for
24 yearsRE: High Rise Building
Hi Kier,
There are several things you need to consider before you start interior finishes, the wet trades, block walls and plastering can start as soon as you removed your temporary support (Props), If you have drywall (gypsum boards), the Building has to be watertight, meaning your curtain wall is already in place on that floor and watertighness or temorary waterproofing measures have been implemented up to a certain level of the building (say in your case the first 15 floors). Joneries requires good weather conditions to start (enviromentally controlled if possible). Extreme weather conditions like the Middle East requires temporary air conditioining before they start any joineries.
The Curtain wall or the cladding of a building can start, if you have adequate safety measures in place, like a catch pan to protect workers from falling objects. They normally require the structure completed up 15 to 20 storey before they start.
THe building services, HVAC, FS, Water, Drainage, etc. Normallly will start from the risers (Main lines) first and then branches out or tee off to each level but it can also be done the other way around.
Note that all your building services should be in place and tested before you close the ceiling.
Best regards,
Daniel
Member for
15 years 1 monthSome projects use a temporary
Some projects use a temporary membrane to allow finishes to proceed due to the risk mentioned earlier about rain running through penetrations, stairways, etc. Remember that you also need to store your materials on a watertight floor/s.
Member for
19 years 10 monthsHi Keir Are you by any chance
Hi Keir
Are you by any chance related to Soren Kierkergaard - the Danish theologian and philosopher?
Best regards
Mike Testro
Member for
17 yearsuseful stuf.. Thanks..
useful stuf.. Thanks..
Member for
19 years 1 monthRE: High rise building
kier,
the interior architectural works of a high rise building has two major division, the wet works(eg. chb & finishes, waterproofing, skimcoating) and the dry works(eg. gypsum wall & ceiling, carpets,fixtures).
The wet works can start as soon as the scaffolds & shorings at the ground level has been removed, this will depend on structural specifications and the curing period of the concrete used. however, the start of wet works is usually deffered depending on the available time and the manner of hand over required by the client.
The dry works usally start when the building is already "partially watertight", this milestone date comes when half of the buildings perimeter glass/glazing is already installed. this consideration vary depending on the height of the building.In your case, you may take the 30th floor glass/glazing installation as the predeccesor of partial watertightness.
hope this helps.
regards
Member for
21 years 9 monthsRE: High rise building
Kier,
Please give me some information about the type of building (Residential/Commercial?)and scope of work (Shell & Core/Fit out?). Do not forget to include some information about the cladding and its method of installation.
Internal Finishes will need protection from external weather conditions - particularly rain & wind. The cladding will only protect you partly until the whole of the Envelope is complete. Service holes, slab perimeter, and stair cores will be of main concern in regards to water ingress.
Regards,
Larry
Member for
19 years 3 monthsRE: High rise building
Hi Larry,
Thanks a lot for the info. I really appreciate in sharing your experience .It helps me a lot.
Can you please enlighten me in the ff.
Wht is the correct timimg to start curtain wall,Hvac ducting,
What do you mean by temporary waterproofing.
Member for
19 years 10 monthsRE: High rise building
Kier,
Maybe you could specify further, are you talking about the architectural works like start of CHB works or it is really what Larry is recommending which is finishing works?
Larry, thanks for the milestone and the logic as well...
Regards,
Arman
Member for
21 years 9 monthsRE: High rise building
Kier,
You need to look at it from a logical sequence of works. After the frame, you have the vertical cladding to consider. Start of Internal Finishes will depend on the cladding progression and temporary waterproofing measures. I would recommend that you insert a milestone ‘building sufficiently waterproofed to start Internal Finishes’.
Also consider the installation rate of cladding Vs Fit-Out - as Internal Finishes is not to surpass cladding.
Regards,
Larry
Member for
22 years 5 monthsRE: High rise building
I would consider the readiness of the area and the number of people, equipment, and materials available at site... you dont want your project to get to crowded...
Member for
19 years 10 monthsRE: High rise building
Kier,
I would suggest for you to have a check first at the construction dead and live loads being considered in the structual design. They might dictate the restrictions.
Regards,
Arman