I want to share our experience in monitoring progress for Railway/Line projects.
for my self I'm using excel (Multiple columns: Km ponits each 5m; zones; area; phases of work; date of achievement of each phase on each Km..) so I can have Three results; Graphical of the progress; Progress by Zone (Area) with possibility to choice the cut off date (Can get the progress on older dates); and the cumulative progress by months or week.
I found this method very useful and easy, please if you have another methods please share.
Member for
20 years 7 months
Member for20 years7 months
Submitted by Stephen Devaux on Fri, 2009-04-17 12:43
Can I nominate the above for the "Favorite quotes about planning" thread? :-)
I basically agree with Gary. However, there are certain occasions when the plan is also not totally linear: when rework has to be performed after a failed test.
If the rework has been pre-planned in fragnet form (as it should have been), then in a sense the plan is still linear. but the "product" has to go through reiteration.
Them semantics things is a bitch, aint they?
Fraternally in PM,
Steve D.
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Fri, 2009-04-17 09:21
Most of my planning is "out of the box", with a degree of blue sky thinking. If we are not all on the same page then I run it up the flagpole and see who salutes. However we MUST reach out for an end to end solution. To touch base together, aim for evolution NOT revolution.
Member for
24 years 9 monthsAhmed,the same may be done
Ahmed,
the same may be done using project management software.
Why do you need Excel?
Member for
15 yearsDear planners; I want to
Dear planners;
I want to share our experience in monitoring progress for Railway/Line projects.
for my self I'm using excel (Multiple columns: Km ponits each 5m; zones; area; phases of work; date of achievement of each phase on each Km..) so I can have Three results; Graphical of the progress; Progress by Zone (Area) with possibility to choice the cut off date (Can get the progress on older dates); and the cumulative progress by months or week.
I found this method very useful and easy, please if you have another methods please share.
Member for
20 years 7 monthsRE: Planning process is linear or is iterative?
Gary wrote;
"The plan itself would be linear.
The planning process however is iterative."
Can I nominate the above for the "Favorite quotes about planning" thread? :-)
I basically agree with Gary. However, there are certain occasions when the plan is also not totally linear: when rework has to be performed after a failed test.
If the rework has been pre-planned in fragnet form (as it should have been), then in a sense the plan is still linear. but the "product" has to go through reiteration.
Them semantics things is a bitch, aint they?
Fraternally in PM,
Steve D.
Member for
16 years 7 monthsRE: Planning process is linear or is iterative?
I think were talking at cross purposes here.
The plan itself would be linear.
The planning process however is iterative
Member for
19 years 10 monthsRE: Planning process is linear or is iterative?
Hi All
I cant help but jump in here.
A fully developed bottom up plan with FS links and one critical path is Linear.
It can be nothing else.
Even when progress is added the linear nature is retained.
In PowerProject there is the option to "Link Around Completed Tasks"
Best regards
Mike Testro
Member for
17 yearsRE: Planning process is linear or is iterative?
Many thanks Gary..
Member for
16 years 7 monthsRE: Planning process is linear or is iterative?
Any time you enter information, analyse it, make changes, then re-analyse, its an iterative process. Planning is definitely an iterative process
example (when developing a schedule):
"Weve got 10km of pipe to put in the ground. How long will that take?"
"4 weeks"
".....thats no good. That pushes us past contract completion"
"OK, I guess well have to hire an additional welding crew. That would bring it down to 2 weeks"
"perfect"
...is an iterative process.
example (when updating a schedule):
"The pump is going to be delivered 2 weeks later than planned -shipment has been delayed by adverse weather"
"Oh dear. That was on the critical path. Is there anything we can do to recover the delay?"
"Well the diesel gen is due in 1 week. we could recover some of it by installing that first, if we can get the foundation done in time."
"OK, pull the boys off the pump foundation, and get them cracking on the diesel gen. Pull extra manpower from the admin building if you need to"
...is an iterative process
Member for
17 yearsRE: Planning process is linear or is iterative?
hmmmmmmmm
what do you mean by Linear vs Iterative.
Member for
17 years 6 monthsRE: Planning process is linear or is iterative?
There is the answer to the question,
If you are using CPM (90%), then it is linear.
Regards,
Safak
Member for
19 yearsRE: Planning process is linear or is iterative?
But with respect I do hear what you say!!
Roger
Member for
19 yearsRE: Planning process is linear or is iterative?
Have you not forgotten singing off the same hymn sheet, or even project cosmic view, or even taking the low hanging fruit
Regards
Roger
Member for
17 yearsRE: Planning process is linear or is iterative?
Hi Tom,
I can imagine many people enjoy reading your programme narrative.
Cheers,
Member for
22 years 4 monthsRE: Planning process is linear or is iterative?
Most of my planning is "out of the box", with a degree of blue sky thinking. If we are not all on the same page then I run it up the flagpole and see who salutes. However we MUST reach out for an end to end solution. To touch base together, aim for evolution NOT revolution.
REMEMBER TEAMWORK MAKES THE DREAM WORK !