the dates that you have now (jab and feb) could be the current forecasted dates while the units could be distributed according to the baseline dates?....
Member for
17 years 4 months
Member for17 years4 months
Submitted by Catherine Barthelemy on Mon, 2009-01-26 04:58
Try looking at your Planned Start and Planned Finish - the start and finish dates for the resource spread will be picked up from these fields - these dates may be different from your start and finish dates
Rgds
Richard
Member for
17 years 4 months
Member for17 years4 months
Submitted by Catherine Barthelemy on Thu, 2009-01-22 11:06
Relationships are straight forward and do not seem to have an effect. And there are no constraints.
Tried different scenarios, changing to Fixed Duration and units with Physical % complete, or even Fixed duration and Units/time with duration, it does not seem to make a difference with the units and which period of time they are allocated. The resource profile settings have not been changed, but then not sure what they are supposed to be...only have a rate and thats that!
Member for
20 years 11 months
Member for20 years11 months
Submitted by Waseem Saber on Thu, 2009-01-22 10:20
Member for
17 years 10 monthsRE: Duration Type/% complete type
Dear Catherine,
the dates that you have now (jab and feb) could be the current forecasted dates while the units could be distributed according to the baseline dates?....
Member for
17 years 4 monthsRE: Duration Type/% complete type
Thank you people!
Am currently trying the different solutions you guys suggested.
Thanks for your help.
Member for
22 years 7 monthsRE: Duration Type/% complete type
Hi Catherine,
Try looking at your Planned Start and Planned Finish - the start and finish dates for the resource spread will be picked up from these fields - these dates may be different from your start and finish dates
Rgds
Richard
Member for
17 years 4 monthsRE: Duration Type/% complete type
Hi!
Relationships are straight forward and do not seem to have an effect. And there are no constraints.
Tried different scenarios, changing to Fixed Duration and units with Physical % complete, or even Fixed duration and Units/time with duration, it does not seem to make a difference with the units and which period of time they are allocated. The resource profile settings have not been changed, but then not sure what they are supposed to be...only have a rate and thats that!
Member for
20 years 11 monthsRE: Duration Type/% complete type
Hi Catherine,
did you check the relationships or any constraints or the resources profile settings.
wondering what different options you have tried??? lets share, we could advice you are on the correct path.
regards
Waseem Saber