Dear Catherine,



the dates that you have now (jab and feb) could be the current forecasted dates while the units could be distributed according to the baseline dates?....

Member for

17 years 4 months

Thank you people!

Am currently trying the different solutions you guys suggested.

Thanks for your help.

Member for

22 years 7 months

Hi Catherine,



Try looking at your Planned Start and Planned Finish - the start and finish dates for the resource spread will be picked up from these fields - these dates may be different from your start and finish dates



Rgds



Richard

Member for

17 years 4 months

Hi!



Relationships are straight forward and do not seem to have an effect. And there are no constraints.

Tried different scenarios, changing to Fixed Duration and units with Physical % complete, or even Fixed duration and Units/time with duration, it does not seem to make a difference with the units and which period of time they are allocated. The resource profile settings have not been changed, but then not sure what they are supposed to be...only have a rate and that’s that!

Member for

20 years 11 months

Hi Catherine,



did you check the relationships or any constraints or the resources profile settings.



wondering what different options you have tried??? lets share, we could advice you are on the correct path.



regards



Waseem Saber