Show P3 trace logic in bar chart

Member for

18 years 8 months

Hello Ali Farhat,



In normally, P3 will show all links if select one. In sometime, If I select a activity and want to see 3 level of predecessors and successors of one in bar chart format.



Please recommend me.

Member for

17 years

Anu,

I didnt get your question perfectly...anyhow, driving relationships are displayed in Gantt and pert chart as solid lines while nondriving relationships are displayed dotted line.

Is that what you want?