Roger

This is unbelievable! Together with the program the ref’manuals should be installed on each pc! And IT should have them for user support.

I sent the pdf.



Regards

Dieter

Member for

19 years

Thanks Dieter,



I ASKED THE IT ABOUT IT,HE DOESN’T GET THIS CD.



Please if you have this file,could you send it to my own mail address:roger_assi@hotmail.com



Sorry for the inconvenience.



Roger

Member for

18 years 9 months

Roger

I assume you or IT installed P6 from the original set of CD’s, On CD no.3 you can find that specific file:

Doku\Moving From P3 to P6\MovingfromP3toP6.pdf.

It is an excellent information for P3 experts.

Regards

Dieter

Member for

19 years

Hi Dieter,



How can i get the pdf file in the documentation cd?



Thanks

Regards,



Roger

Member for

18 years 9 months

Roger

Equal is what belongs to exactly that node, under everything below, e.g if you have a code "location" with continent on level 1, country on level 2, region on level 3 and yu ask for Europe, it will show only those where Europe is assigned - not e.g. Germany, UK... - whereas under will show all with Europe and Germany, UK, and...

Maybe I understood your item with bars:

Within the Gantt chart: right mouse button --> Bar chart options --> collapsed bars --> unmark "Show relationships...".

A clean summary bar: Within the Gantt chart: right mouse button --> Bars --> bar settings --> unmark "Show when collapsed"

"SOMETIMES SOME BAR NOT LINK TO THE OTHER WHEN WE DON’T HAVE WORK IN THE ACTIVTY"??? Not due to capitals. Can the reason be a week-end?

Dieter

Member for

19 years

Thanks again Dieter,



Is under same like equal in filtration??



For the SUMMARISE BAR,IT APPEARS VERTICAL LINE INSIDE THE BAR,HOW WE CAN REMOVE IT?AND SOMETIMES SOME BAR NOT LINK TO THE OTHER WHEN WE DON’T HAVE WORK IN THE ACTIVTY.



Thanks


Member for

18 years 9 months

Roger

Sorry your question concerning the bars I didn’t understand. Maybe you mean something under:

Within the Gantt chart: right mouse button --> Bar chart options --> collapsed bars or general. If not, please explain.

"Is Under" means: in your hierarchical structure everything nelow a certain node.

Regards

Dieter

Member for

19 years

Hi Jackie,



Regarding the resources,32000m3,we can write it like that:

32,000 m3with commas....

For the bar,i know from the format bars,but i mean in the Gant Chart,also if we have non working days ,it shows seperation of bars.



Thanks again.

Member for

20 years 7 months

Hi Roger



By accessing View / Bars from your menu or clicking on your Bars icon you can set up the way you want your bars to display.



Jackie

Member for

19 years



Also Dieter,



When we summarise all the activities in one bare,it appears black line in the bar,i think the symbol of many activities starting at this date,could we delete it??



Thanks again

Member for

19 years

Thanks Dieter,



What the meaning of "is under" in the filtration.



So if we have one thirty two thousand m3,there is no format inside p6 to write :32,000..and not 32000.



Thanks a lot.



Roger

Member for

18 years 9 months

Roger

ps: If you want to enter big numbers just do it without comma for thousand.

Dieter

Member for

18 years 9 months

Roger

The concept for codes is different to P3 - they are hierarchical. WR no longer exists for the codes - it does in other areas. A nice feature in P6 is "Is under".

For the differences between P3 and P6 there is an excellent PDF on the documentation CD.

Regards

Dieter