Setting Work Days?

Member for

18 years 5 months

That is exactly how i figured it out... and it is for sure the way to go



Thanks!!!!



Keep the advice coming!!!



Ken Barrett

Member for

17 years 10 months

I would also recommend on your display column pick the calender display option, and you can change your calender on your activity. I find that much easier because the schedule i am dealing with involves levee and river work with 6 different calenders, and trust me, the Corps of Engineers has many restriction and simply tie your hands all the time.

Member for

18 years 9 months

Member for

18 years 5 months

I figured out that my activity calendar was wrong. I had my project calendar set to 7 days, resource calendar set to 7 days but my activity calendar was set to 5 days...



I appricate all your help. This site is an absolute god send for me. I am a 26 year old engineer with little field experience and even less planning experience, but trying to produce scheduling/planning/budgeting/everything else... just flying by the seat of my pants...hahahah... as they say, sink or swim!!

Member for

18 years 9 months

Did you check if the seven day work week calendar really was created as named?

I don’t know of such a restriction. In neneral we have this situation: 5 work days in Europe (Engineering), 6 with Friday off (Construction) and 7 for lead times.... It works.

Dieter

Member for

18 years 5 months

Thank you for help,



I have my activity type as Task Dependent, and my calendar is set to 7 day work week, still no time scheduled for weeeknds... any other possible fixes?

Member for

18 years 9 months

Hi Ken

The project calendar is just a default for new activities.

I assume you want to plan with fixed durations. So:

- Activity type: Task dpendent

- Task calendar: the one with working time during weekend.



Regards

Dieter