Resource Costs Back Ended

Member for

19 years 5 months

Thanks Brad & Andrew.



I’ve been busy this morning trying to get this report perfect. Yes I forget to amend the resource duration from 5 days to 1. So Andrew’s tip worked. My report didnt help as it was taking the data from the baseline and not remaining -doh. Moscow.

Member for

20 years 11 months

Hi Mark.

You can’t assign the resource to a milestone type activity in P5.

If you are using P6 you can manually set the resource consumption to the very last day of activity. If you have P5 - you may try Expense Item with ’End of Activity’ Accrual Type or try resource assignment with Original Lag = 4 and Original Duration = 1.

Hope this will help you.

Regards,

Andrew