P6 Interproject Relationship Imports

Member for

17 years 11 months

That won’t help you maintain existing links in your existing project that you want to update.



That will merely keep the links in your new update.

Member for

20 years 11 months

When you import you should untick the relationship between only copied activities, this should be able to bring all the relationships with other projects.



hope this helps.....



Waseem Saber