Total Float P3e

Member for

22 years

Graeme,



Before you schedule the programme, go to options and

Select ’’retain Logic ’’ or ’’Progress Override’’ to see how it changes.



I think it works.



Wasantha

Member for

20 years 11 months

Graeme,



check there must be some constraints assigned to some of your milestone activities, there is a possibility one of those activity is constrained and actually finished late, thus causing this float issue, hope this is the scenario and it works, otherwise, let us know, if you found the solution, this is a intresting situation worth consideration.



cheers



Waseem Saber

Member for

22 years 4 months

Thanks everyone for the responses.



Paul, With regard to the system showing null total float, that’s exactly what I want to show. Unfortunately my system does not show this. I don’t know why...



Rodel, I had checked my Project Settings date previously, I had not entered a date in the must finish by date tab.



Ronald, I think this P5 Service patch will help.



Once again everyone thanks for your help.



Graeme

Member for

22 years 10 months

Graeme,



This condition was introduced two years ago with the release of P5. It was ’fixed’ in the first P5 service patch. (By the way, completed activities really do have float but you really need to understand complex CPM theory in order to understand why.)

Member for

19 years

Graeme,



Check your Project Settings Date. It happens only when Must Finish By date is higher than Finish Date.



To check: Select Enterprise-> Project then select your Project to check and click Date tab. If "Must Finish By" date is higher than "Finish" Date then remove the "Must Finish By" date.



Hope this help.



Rodel

Member for

24 years 7 months

When I make activities as complete my system displays nul total float, that is there is no value displayed in the total float field.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au