Oracle Primavera - PM6 Member for 18 years 5 months Member for 18 years 6 months Submitted by Patricia Le Clainche on Tue, 2007-11-13 14:24 Permalink RE: P3e - Resource If I understand your problem correctly : On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them. Best regards. Log in or register to post comments
Member for 18 years 5 months Member for 18 years 6 months Submitted by Patricia Le Clainche on Tue, 2007-11-13 14:24 Permalink RE: P3e - Resource If I understand your problem correctly : On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them. Best regards.
Member for
18 years 5 monthsRE: P3e - Resource
If I understand your problem correctly :
On Activity View, show the Bottom Layout, and on "Resource tab", add your resources Ids, and then, you just have to fill the Remaining Units ( = Remaining Labor Units) for each of them.
Best regards.