If your project database (usually PMDB) was created with P5.0 and a SP prior to 3 or 4 (pl check POINT) you should also upgrade it with the corresponding Primavera utility, because Primavera changed the it’s fields, stucture and queryes.



Cheers

Member for

19 years 5 months

red herring! Not sure how this happened but the activity in the baseline wasnt the same as the current project. So now I need to find out how this happened!

Member for

19 years 5 months

Joao, Not sure what you mean but sp4 is shown when going to "about primavera".

Member for

22 years 7 months

BTW: Have you updated the database when applying the SP?