Displaying Calender Days

Member for

18 years 6 months

Bri,



Rodel is right, but is using UDF’s is just a frig, P5 won’t do what you want I’m afraid.



Whomever you are showing the plan to can just look at start and finish dates to get an idea of the calendar duration.



Oliver

Member for

19 years

Brian,



You can use User Defined Fields and update that using Global change or import the data from excel spreadsheets. That will do the trick.



Regards,

Rodel

Member for

18 years 2 months

Thanks for the info. Oliver.



What I’m trying to do is display calender days under original duration or a similar column. I’m running into some confusion when presenting my schedules that are based on a 5 day 40hr work week. If there is any way to take the overall time from the start date to finish date and display that, that would work.

Member for

18 years 6 months

Brian,



You can only show original duration and duration.



You can’t show the elapsed calendar days.



Also, P5 calculates durations based on the equivalant hours entered spread across the no of ’hours per period’ in the admin preferences, so if you use multiple calendars with different number of hours per period, then the duration columns won’t show the correct duration for all actvities.



Oliver