Brand New to P5 - Import questions

Member for

18 years 6 months

I agree with David,



you must have relationships between your activities in order to schedule the work. Otherwise all activities will move to the data date as there is nothing telling them they can’t start immediately.

Member for

21 years

Hi There,



You are importing activities.Ok.



But if there is no relationship b/w activities, whether you import it or not, it is logical to see the start dates as data dates on the program.



Start dates, durations and finish dates are not enough to create a cpm. Relationship of those activites has to be defined as well.



Hope this helps

Member for

18 years 5 months

I am not importing relationships, just activities.



Can you create WBS by importing?


Member for

21 years

Hi There,



Did you check the relationship of activities?



I mean, while importing or exporting are you also importing or exporting predecessors or successors of activities.



It may cause such problem.



Regards,