I know this is not what youre asking, but in case you dont know, you can show (with a tick) which activities are driving, within the Predecessors or Relationships/Predecessors tabs.
To show driving relationships only in a layout is an existing enhancement request, according to the Primavera Knowledgebase.
Member for
19 years 6 months
Member for19 years6 months
Submitted by David Podmore on Wed, 2007-01-03 03:55
to do that you need the un progress baseline schedule
What I normally do is since some of the activity is already completed and finish so it is very hard to filter and trace all the activity which is linked to this particular activity,
to filter that first step is use the baseline schedule (With the same logic sequence) (make a copy) - add a finish no later constraint in the tail activity with a very very early day 2 year before its early finish day or something like that
Schedule the plan
Filter the activity with excessive negative float,
Remove the constraint
Schedule the plan again
Then you will have all the activity that have assoication (link) with this activity
Sort the activity by total float
the lease float activities are the critical path for that particular activity, and the rest is on the critical path but not necessary as the critical activity
Member for
19 years 3 monthsRE: How to filter out only those activities driving a task?
There is another existing enhancement request to show which relationships are driving, as a column.
Member for
19 years 3 monthsRE: How to filter out only those activities driving a task?
I know this is not what youre asking, but in case you dont know, you can show (with a tick) which activities are driving, within the Predecessors or Relationships/Predecessors tabs.
To show driving relationships only in a layout is an existing enhancement request, according to the Primavera Knowledgebase.
Member for
19 years 6 monthsRE: How to filter out only those activities driving a task?
Thanks for that Alex.
Its not the simple answer I was hoping for! Ah well, I guess we will have to wait for Primavera to add it as a function.
Trace Logic is the closest we have found to an answer but its still not as good as "Display driving links only" in Pertmaster.
Again, thanks for your time.
David
Member for
22 years 8 monthsRE: How to filter out only those activities driving a task?
David
to do that you need the un progress baseline schedule
What I normally do is since some of the activity is already completed and finish so it is very hard to filter and trace all the activity which is linked to this particular activity,
to filter that first step is use the baseline schedule (With the same logic sequence) (make a copy) - add a finish no later constraint in the tail activity with a very very early day 2 year before its early finish day or something like that
Schedule the plan
Filter the activity with excessive negative float,
Remove the constraint
Schedule the plan again
Then you will have all the activity that have assoication (link) with this activity
Sort the activity by total float
the lease float activities are the critical path for that particular activity, and the rest is on the critical path but not necessary as the critical activity
HTH
ALex