How to filter out only those activities driving a task?

Member for

19 years 3 months

I know this is not what you’re asking, but in case you don’t know, you can show (with a tick) which activities are driving, within the Predecessors or Relationships/Predecessors tabs.



To show driving relationships only in a layout is an existing enhancement request, according to the Primavera Knowledgebase.

Member for

19 years 6 months

Thanks for that Alex.



It’s not the simple answer I was hoping for! Ah well, I guess we will have to wait for Primavera to add it as a function.



Trace Logic is the closest we have found to an answer but it’s still not as good as "Display driving links only" in Pertmaster.



Again, thanks for your time.



David

Member for

22 years 8 months

David



to do that you need the un progress baseline schedule



What I normally do is since some of the activity is already completed and finish so it is very hard to filter and trace all the activity which is linked to this particular activity,

to filter that first step is use the baseline schedule (With the same logic sequence) (make a copy) - add a finish no later constraint in the tail activity with a very very early day 2 year before its early finish day or something like that

Schedule the plan

Filter the activity with excessive negative float,

Remove the constraint

Schedule the plan again



Then you will have all the activity that have assoication (link) with this activity

Sort the activity by total float

the lease float activities are the critical path for that particular activity, and the rest is on the critical path but not necessary as the critical activity



HTH



ALex