Duration calculation by calendar

Member for

23 years 8 months

sorry to let us know, no change in P6. the "duration" is determined by user perference within the "calculated dates" by defined calendar.



Which means the display value in duration is keep on changing if user preference is changed.

Member for

21 years

Version 5 is the same. No "rumors" that version 6 will be any different BUT will probably allow a work-around.

Member for

19 years 3 months

Dave,

Thanks, I just discussed this with our admin. It does pose a problem to our field plans that do not work 1-8-5. The default for our database has to be 1-8-5 for mfg. Do you know if version 5 has address this?

BTW, 3-1 would have been easy with Utd. It is going to be a tough season as an arab.



Alex,

1-8-5 is 1 shift, 8 hours, 5 days. Therefore 2-10-7 is 2 shifts, 10 hours, 7 days. I don’t know if this is just Canadian terminology, but it makes sense to me.



Cheers and Thanks for the help.



Dave

Member for

21 years

Let me guess.



You changed all the activity’s calandars, but mysteriously all the durations for the summary bars have stayed the same?



In P3e all summary durations are calculated as the number of working periods between the start and finish of the summary bar as measured on the database’s default calandar. The default calandar is "ticked in the global calandar display.

Member for

22 years 9 months

Dave



1 8 5 ??



1:oo - 8:00 5 days??

or

1 Days 8:00 - 5:00

or

1 shift, 8 hrs days and 5 days??



Please clarify



Alex