Alex,



Yeah,I am importing the data into excel right now.But its bit tedious when u have to do a Weekly Peaks report for a project with duration of 24 months. I hope primavera will add this feature in the ver.5(I have pointed out this to them,anyway)



cheers,

vamsi

Member for

22 years 8 months

Vamis



One work around is to use resource table by date

Export the table to Excel run a function to select the max from each week/month/quater.



That should give u a table with peak resource usage @ the time period you wanted



Cheers



Alex