Methods of Construction (C. INTERIORS)

Member for

20 years 2 months

Activity ID Activity description

MOBI-01 Site Mobilisation

MOBI-03 Fencing work

MOBI-02 Establish Temporary Servicies

EARTH-03 Shoring ( I- Section Concrete pannel )

EARTH-02 Priliminary Earth Work

EARTH-04 1st Phase Excavation

EARTH-05 2nd stage Excavation & concrete panel instlation

EARTH-07 Carting Excess Excavated material

EARTH-06 Dewaterring

EARTH-08 Formation of Deep Area

EARTH-09 Compaction & Formation for Raft bed

FOUND-02 Guniting

FOUND-01 PCC Deep Area

FOUND-03 PCC below RAFT

FOUND-05 Rubberised Bitumen Coating

FOUND-06 Waterproofing & Screed Protection

FOUND-04 Vertical area water proffing

FOUND-07 Steel work for RAFT

MEP-01 Drainage pipe laying and testing (UG Drainage)

FOUND-08 Raft Slab Casting (Part A&B)

SUB-01 Retaining Wall

SUB-06 Ramp Work

SUB-02 Shear Wall & Lift Core Wall

SUB-03 steel work for column

SUB-04 Form work for column

SUB-05 Column casting For GF Slab

SUB-07 Decking Work for G.F Slab

SUB-08 Steel Work for G.F Slab

SUB-09 MEP sleves & conduits for G.F Slab

SUB-10 Ground Floor Slab Casting

SUB-11 Deshuttering

SUB-12 Ramp Side RCC wall

SUB-13 Rcc planters & side wall / upstaand

SUCO-GF-02 steel work for column/A

SUCO-GF-03 Form work for column/A

SUCO-GF-01 Shear Wall /A

SUCO-GF-04 Column casting For 1F/A Slab

SUCO-GF-05 Decking work for 1F/ASlab

SUCO-GF-07 Steel Work for 1F/A Slab

SUCO-GF-08 MEP sleves & conduits for 1.F/A Slab

SUCO-GF-09 First Floor Slab Casting[Part-A ]

SUCO-GF-10 Deshuttring PART- A

SUCO-GF-12 steel work for column

SUCO-GF-11 Shear Wall & Lift Core Wall

SUCO-GF-13 Form work for column

SUCO-GF-14 Column casting For 1F Slab

SUCO-GF-15 Decking work for 1F Slab

SUCO-GF-17 Steel Work for 1F Slab

SUCO-GF-18 MEP sleves & conduits for 1.F Slab

SUCO-GF-19 First Floor Slab Casting[Part-B ]

SUCO-GF-20 Deshuttering PART- B

SUCO-GF-16 Ramp Side RCC wall

SUCO-1F-01 steel work for column/A

SUCO-1F-02 Form work for column/A

SUCO-1F-03 Shear Wall /A

SUCO-1F-04 Column casting For 2F/A Slab

SUCO-1F-05 Decking work for 2F/ASlab

SUCO-1F-06 Steel Work for 2F/A Slab

SUCO-1F-07 MEP sleves & conduits for 2.F/A Slab

SUCO-1F-08 Second Floor Slab Casting[Part-A ]

SUCO-1F-09 Deshuttering PART- A

SUCO-1F-11 Steel work for column

SUCO-1F-12 Form work for column

SUCO-1F-10 Shear Wall & Lift Core Wall

SUCO-1F-13 Column casting For 2F Slab

SUCO-1F-14 Decking Work for 2F Slab

SUCO-1F-15 Steel Work for 2F Slab

SUCO-1F-16 MEP sleves & conduits for 2 F Slab

SUCO-1F-17 Second Floor Slab Casting [Part-B ]

SUCO-1F-18 Deshuttering PART- B

SUCO-2F-01 steel work for column/A

SUCO-2F-02 Form work for column/A

SUCO-2F-03 Shear Wall /A

SUCO-2F-04 Column casting For 3F/A Slab

SUCO-2F-05 Decking work for3F/ASlab

SUCO-2F-06 Steel Work for3F/A Slab

SUCO-2F-07 MEP sleves & conduits for 3 F/A Slab

SUCO-2F-08 ThirdFloor Slab Casting[Part-A ]

SUCO-2F-09 Third floor slab Deshuttering PART- A

SUCO-2F-11 steel work for column

SUCO-2F-10 Shear Wall

SUCO-2F-12 Form work for column

SUCO-2F-13 Column casting For 3F Slab

SUCO-2F-14 Decking Work for 3F Slab

SUCO-2F-15 Steel Work for 3F Slab

SUCO-2F-16 MEP sleves & conduits for 3F Slab

SUCO-2F-17 Third Floor Slab Casting [Part-B]

SUCO-2F-18 Deshuttering PART- B

SUCO-3F-01 steel work for column/A

SUCO-3F-02 Form work for column/A

SUCO-3F-03 Shear Wall /A

SUCO-3F-04 Column casting For 4F/A Slab

SUCO-3F-05 Decking work for 4F/ASlab

SUCO-3F-06 Steel Work for4F/A Slab

SUCO-3F-07 MEP sleves & conduits for4.F/A Slab

SUCO-3F-08 Fourth Floor Slab Casting[Part-A ]

SUCO-3F-09 Deshuttering PART- A

SUCO-3F-11 steel work for column

SUCO-3F-10 Shear Wall & Lift Core Wall

SUCO-3F-12 Form work for column

SUCO-3F-13 Column casting For 4F Slab

SUCO-3F-14 Decking Work for 4F Slab

SUCO-3F-15 Steel Work for 4F Slab

SUCO-3F-16 MEP sleves & conduits for 4F Slab

SUCO-3F-17 Fourth Floor Slab Casting [Part-B

SUCO-3F-18 Deshuttering 4 F slab PART- B

SUCO-4F-01 steel work for column/A

SUCO-4F-02 Form work for column/A

SUCO-4F-03 Shear Wall /A

SUCO-4F-04 Column casting For5F/A Slab

SUCO-4F-05 Decking work for 5F/ASlab

SUCO-4F-06 Steel Work for 5F/A Slab

SUCO-4F-07 MEP sleves & conduits for 5F/A Slab

SUCO-4F-08 Fifth Floor Slab Casting[Part-A ]

SUCO-4F-09 Deshuttering PART- A

SUCO-4F-11 steel work for column

SUCO-4F-10 Shear Wall & Lift Core Wall

SUCO-4F-12 Form work for column

SUCO-4F-13 Column casting For 5F Slab

SUCO-4F-14 Decking Work for 5.F Slab

SUCO-4F-15 Steel Work for 5.F Slab

SUCO-4F-16 MEP sleves & conduits for 5.F Slab

SUCO-4F-17 Fifth Floor Slab [Part-B]

SUCO-4F-18 Deshuttering 5F Slab PART- B

SUCO-5F-01 steel work for column/A

SUCO-5F-02 Form work for column/A

SUCO-5F-03 Shear Wall /A

SUCO-5F-04 Column casting For 6F/A Slab

SUCO-5F-05 Decking work for 6F/ASlab

SUCO-5F-06 Steel Work for 6F/A Slab

SUCO-5F-07 MEP sleves & conduits for 6 F/A Slab

SUCO-5F-08 Sixth Floor Slab Casting[Part-A ]

SUCO-5F-09 Deshuttering PART- A

SUCO-5F-11 steel work for column

SUCO-5F-10 Shear Wall & Lift Core Wall

SUCO-5F-12 Form work for column

SUCO-5F-13 Column casting For 6 F Slab

SUCO-5F-14 Decking Work for 6.F Slab

SUCO-5F-15 Steel Work for 6.F Slab

SUCO-5F-16 MEP sleves & conduits for 6.F Slab

SUCO-5F-17 Sixth Floor Slab Casting PART-B

SUCO-5F-18 Deshuttering PART- B

SUCO-6F-01 steel work for column/A

SUCO-6F-02 Form work for column/A

SUCO-6F-03 Shear Wall /A

SUCO-6F-04 Column casting For 7F/A Slab

SUCO-6F-05 Decking work for 7F/ASlab

SUCO-6F-06 Steel Work for 7F/A Slab

SUCO-6F-07 MEP sleves & conduits for 7F/A Slab

SUCO-6F-08 Seventh Floor Slab Casting[Part-A ]

SUCO-6F-09 Deshuttering PART- A

SUCO-6F-11 steel work for column

SUCO-6F-10 Shear Wall & Lift Core Wall

SUCO-6F-12 Form work for column

SUCO-6F-13 Column casting For 7F Slab

SUCO-6F-14 Decking Work for 7.F Slab

SUCO-6F-15 Steel Work for 7.F Slab

SUCO-6F-16 MEP sleves & conduits for 7.F Slab

SUCO-6F-17 Seventh Floor Slab Casting (PART-B)

SUCO-6F-18 Deshuttering PART- B

SUCO-7F-01 steel work for column/A

SUCO-7F-02 Form work for column/A

SUCO-7F-03 Shear Wall /A

SUCO-7F-04 Column casting For RF /A Slab

SUCO-7F-05 Decking work for RF/A Slab

SUCO-7F-06 Steel Work for RF/A Slab

SUCO-7F-07 MEP sleves & conduits for RF/A Slab

SUCO-7F-08 Roof Floor Slab Casting[Part-A ]

SUCO-7F-09 Deshuttering PART- A

SUCO-7F-11 steel work for column

SUCO-7F-10 Shear Wall & Lift Core Wall

SUCO-7F-12 Form work for column

SUCO-7F-13 Column casting For RF Slab

SUCO-7F-14 Decking Work for R.F Slab

SUCO-7F-15 Steel Work for R.F Slab

SUCO-7F-16 MEP sleves & conduits for R.F Slab

SUCO-7F-17 Roof Slab Casting (PART-B)

SUCO-7F-18 Deshuttering PART- B

SUCO-HC-01 steel work for column

SUCO-HC-02 Shear Wall & Lift Core Wall

SUCO-HC-03 Form work for column

SUCO-HC-05 Parapet Wall

SUCO-HC-04 Column casting

SUCO-HC-07 Swimming pool Shell

SUCO-HC-10 Pool Deck

SUCO-HC-06 Decking Work for HC Slab

SUCO-HC-09 MEP sleves & conduits for HC Slab

SUCO-HC-08 Steel Work for HC Slab

SUCO-HC-11 Helth Club Slab Casting

SUCO-HC-12 Deshuttering

SUCO-UR-03 steel work for column

SUCO-UR-02 Shear Wall & Lift Core Wall

SUCO-UR-04 Form work for column

SUCO-UR-05 Parapet Wall above HC

SUCO-UR-01 Column casting For lift m/c room

SUCO-UR-06 Decking Work for lift m/c room

SUCO-UR-08 MEP sleves & conduits for lift m/c room

SUCO-UR-07 Steel Work for lift m/c room

SUCO-UR-09 Lift m/c room Slab

BLO-B-01 cleaning

BLO-B-02 Block layout and checking

BLO-B-03 Block work in Basement

BLO-B-04 R.C.C Lintel

PLAS-B-01 Wall Plaster - Basement

PLAS-B-02 Celing Plaster-Basement

FLO-B-02 marble flooring to lift loby

A0EXAV-09 Earth filling above raft 8’’tk

FLO-B-04 Marble Wall Clading to Lift Loby

FLO-B-05 4’’ PCC with mesh

FLO-B-07 Pump/ Store room flooring

FLO-B-01 Car parking /Driveway Floor Finishing

FLO-B-03 floor finish to water tank area

FLO-B-06 Wall clading to Pump room

FLO-B-08 Thrishold

FAL-B-01 False Ceiling

PANT-B-01 Internal wall & ceiling painting

PANT-B-02 Anticarbonation painting in wall

PANT-B-03 Final internal painting

CARP-B-01 Fixing of Door Frame

CARP-B-02 Fixing of Door Shutter

A0MIS-01 Substation Trenching Work

MET-01 Aluminium (LOUVER WORK) Substation

PANT-GF-01 Transformer room painting

A0PRO-17 Dewa Inspection Substation

A0PRO-18 Sub station hand over to DEWA

BLO-GF-01 cleaning

BLO-GF-02 Block layout and checking

BLO-GF-03 Internal Block Work

BLO-GF-04 Block work- GF

A0ON-GF-08 R.C.C Lintel

PLAS-GF-02 Celing Plaster- GF

PLAS-GF-01 Wall Plaster GF

WPR-GF-02 GF- Parking W/P

WPR-GF-01 Water proof coating to Wet areas

WPR-GF-03 Vertical side w/p of wet area

FLO-GF-08 Wet area wall clading ( garbage room)

FLO-GF-06 Wet area flooring (ceramic tiles)

WPR-GF-04 Water proofing to substation slab roof

FLO-GF-02 Floor Screed for Electrical Room/gym/

FLO-GF-01 4’’ PCC with mesh

FLO-GF-03 Floor Screed for M.hall

FLO-GF-05 Floor Screed for Electricaal Sub-station

FLO-GF-04 Car parking /Driveway Floor Finishing

FLO-GF-07 Floor Screed for Gym / Shop

FLO-GF-09 Mosaic flooring to stair floor & landing area

FLO-GF-10 Floor Screed for Gen. Room

FLO-GF-11 Store and other room flooring

FLO-GF-12 mosaic step

FLO-GF-14 Marble flooring to Entrance passage

FLO-GF-15 mosaic skirting for steps

FLO-GF-13 Threshold

FLO-GF-17 Fixing Marble Steps

FLO-GF-16 Marble Wall Clading to Lift Loby

FAL-GF-01 False Ceiling

PANT-GF-02 Internal wall & ceiling painting

PANT-GF-03 Final internal painting

PANT-GF-04 Anticarbonation painting in wall

CARP-GF-01 Fixing of Door Frame

CARP-GF-02 Fixing of Door Shutter

CARP-GF-03 Fixing of Kitchen Cabinet

CARP-GF-04 Fixing of Wardrobes

MEP-GF-07 Sanitary fixing & Mixer

BLO-1F-01 Cleaning

BLO-1F-02 Block layout and checking

BLO-1F-04 Block work- 1F

BLO-1F-03 Internal Block Work

A0ON-1F-07 R.C.C Lintel

PLAS-1F-02 Celing Plaster- 1F

PLAS-1F-01 Wall Plaster - 1F

WPR-1F-02 Water proof coating to Wet areas

WPR-1F-03 Vertical side w/p of wet area

FL0-1F-10 Wet area -Ceramic Wall Clading

FL0-1F-04 Wet area- Ceramic flooring

FL0-1F-02 Floor Screed for Electrical Room

FL0-1F-01 Ceramic flooring inside room

FL0-1F-03 Ceramic tiling to balconey and terrase

FL0-1F-05 Ceramic tile to entrance loby

FL0-1F-06 Marble flooring to Corridor

FL0-1F-07 Skirting

FL0-1F-09 Corridor Wall Clading-Ceramic

FL0-1F-08 Telephone room & other room flooring

FL0-1F-11 Threshold

FAL-1F-01 1F-Baalcony False Ceiling

FAL-1F-02 False Ceiling

PANT-1F-01 Internal wall & ceiling painting

PANT-1F-02 Final internal painting

CARP-1F-01 Fixing of Door Frame

CARP-1F-02 Fixing of Door Shutter

CARP-1F-03 Fixing of Kitchen Cabinet

CARP-1F-04 Fixing of Wardrobes

MEP-1F-08 Bath Tub Fixing

MEP-1F-09 Sanitary fixing & Mixer

BLO-2F-01 clening

BLO-2F-02 Block layout and checking

BLO-2F-04 Block work- 2F

BLO-2F-03 Internal Block Work

A0ON-2F-07 R.C.C Lintel

PLAS-2F-01 Wall Plaster - 2F

PLAS-2F-02 Celing Plaster- 2F

WPR-2F-02 Water proof coating to Wet areas

WPR-2F-03 Vertical side w/p of wet area

FLO-2F-10 Wet area -Ceramic Wall Clading

FLO-2F-05 Wet area- Ceramic flooring

FLO-2F-01 Ceramic tile to entrance loby

FLO-2F-02 Floor Screed for Electrical Room

FLO-2F-03 Ceramic tile iside the room

FLO-2F-04 Ceramic tiling to balconey and terrase

FLO-2F-06 Marble flooring to Corridor

FLO-2F-07 Skirting

FLO-2F-09 Corridor Wall Clading-Ceramic

FLO-2F-08 Telephone room & other room flooring

FLO-2F-11 Threshold

FAL-2F-01 2F-Baalcony False Ceiling

FAL-2F-02 False Ceiling

PANT-2F-01 Internal wall & ceiling painting

PANT-2F-02 Final internal painting

CARP-2F-01 Fixing of Door Frame

CARP-2F-02 Fixing of Door Shutter

CARP-2F-03 Fixing of Kitchen Cabinet

CARP-2F-04 Fixing of Wardrobes

MEP-2F-08 Bath Tub Fixing

MEP-2F-09 Sanitary fixing & Mixer

BLO-3F-01 cleaning

BLO-3F-02 Block layout and checking

BLO-3F-03 Block work -3F

BLO-3F-04 Internal Block Work

A0ON-3F-07 R.C.C Lintel

PLAS-3F-01 Wall Plaster - 3F

PLAS-3F-02 Celing Plaster- 3F

WPR-3F-02 Water proof coating to Wet areas

WPR-3F-03 Vertical side w/p of wet area

FLO-3F-08 Wet area -Ceramic Wall Clading

FLO-3F-03 Wet area- Ceramic flooring

FLO-3F-01 Ceramic tiling to balconey and terrase

FLO-3F-02 Ceramic tile iside the room

FLO-3F-06 Floor Screed for Electrical Room

FLO-3F-04 Ceramic tile to entrance loby

FLO-3F-05 Skirting

FLO-3F-07 Telephone room & other room flooring

FLO-3F-09 Marble flooring to Corridor

FLO-3F-10 Threshold

FLO-3F-11 Corridor Wall Clading-Ceramic

FAL-3F-01 3F-Baalcony False Ceiling

FAL-3F-02 False Ceiling

PANT-3F-01 Internal wall & ceiling painting

PANT-3F-02 Final internal painting

CARP-3F-01 Fixing of Door Frame

CARP-3F-02 Fixing of Door Shutter

CARP-3F-03 Fixing of Kitchen Cabinet

CARP-3F-04 Fixing of Wardrobes

MEP-3F-08 Bath Tub Fixing

MEP-3F-09 Sanitary fixing & Mixer

BLO-4F-01 cleaning

BLO-4F-02 Block layout and checking

BLO-4F-04 Block work -4F

BLO-4F-03 Internal Block Work

A0ON-4F-07 R.C.C Lintel

PLAS-4F-01 Wall Plaster - 4F

PLAS-4F-02 Celing Plaster- 4F

WPR-4F-02 Water proof coating to Wet areas

WPR-4F-03 Vertical side w/p of wet area

FLO-4F-09 Wet area -Ceramic Wall Clading

FLO-4F-08 Wet area- Ceramic flooring

FLO-4F-02 Floor Screed for Electrical Room

FLO-4F-01 Ceramic tile to entrance loby

FLO-4F-03 Ceramic tiling to balconey and terrase

FLO-4F-05 Marble flooring to Corridor

FLO-4F-04 Ceramic tile iside the room

FLO-4F-10 Telephone room & other room flooring

FLO-4F-06 Corridor Wall Clading-Ceramic

FLO-4F-07 Skirting

FLO-4F-11 Threshold

FAL-4F-01 4F-Balcony False Ceiling

FAL-4F-02 False Ceiling

PANT-4F-01 Internal wall & ceiling painting

PANT-4F-02 Final internal painting

CARP-4F-02 Fixing of Door Frame

CARP-4F-03 Fixing of Door Shutter

CARP-4F-01 Fixing of Kitchen Cabinet

CARP-4F-04 Fixing of Wardrobes

MEP-4F-08 Bath Tub Fixing

MEP-4F-09 Sanitary fixing & Mixer

BLO-5F-01 cleaning

BLO-5F-02 Block layout and checking

BLO-5F-04 Block work -5F

BLO-5F-03 Internal Block Work

A0ON-5F-07 R.C.C Lintel

PLAS-5F-01 Wall Plaster - 5F

PLAS-5F-02 Celing Plaster- 5F

WRP-5F-02 Water proof coating to Wet areas

WRP-5F-03 Vertical side w/p of wet area

FLO-5F-10 Wet area -Ceramic Wall Clading

FLO-5F-04 Wet area- Ceramic flooring

FLO-5F-01 Floor Screed for Electrical Room

FLO-5F-03 Ceramic tile to entrance loby

FLO-5F-06 Marble flooring to Corridor

FLO-5F-05 Ceramic tile iside the room

FLO-5F-02 Ceramic tiling to balconey and terrase

FLO-5F-08 Telephone room & other room flooring

FLO-5F-07 Corridor Wall Clading-Ceramic

FLO-5F-09 Skirting

FLO-5F-11 Threshold

FAL-5F-01 5F-Balcony False Ceiling

FAL-5F-02 False Ceiling

PANT-5F-01 Internal wall & ceiling painting

PANT-5F-02 Final internal painting

CARP-5F-02 Fixing of Door Frame

CARP-5F-03 Fixing of Door Shutter

CARP-5F-01 Fixing of Kitchen Cabinet

CARP-5F-04 Fixing of Wardrobes

MEP-5F-08 Bath Tub Fixing

MEP-5F-09 Sanitary fixing & Mixer

BLO-6F-01 cleaning

BLO-6F-02 Block layout and checking

BLO-6F-03 Block work -6F

BLO-6F-04 Internal Block Work

A0ON-6F-07 R.C.C Lintel

PLAS-6F-01 Wall Plaster - 6F

PLAS-6F-02 Celing Plaster- 6F

WRP-6F-02 Water proof coating to Wet areas

WRP-6F-03 Vertical side w/p of wet area

FLO-6F-11 Wet area -Ceramic Wall Clading

FLO-6F-05 Wet area- Ceramic flooring

FLO-6F-01 Floor Screed for Electrical Room

FLO-6F-03 Ceramic tile to entrance loby

FLO-6F-04 Ceramic tile iside the room

FLO-6F-02 Ceramic tiling to balconey and terrase

FLO-6F-06 Skirting

FLO-6F-09 Marble flooring to Corridor

FLO-6F-10 Corridor Wall Clading-Ceramic

FLO-6F-07 Telephone room & other room flooring

FLO-6F-08 Threshold

FAL-6F-01 6F-Balcony False Ceiling

FAL-6F-02 False Ceiling

PANT-6F-01 Internal wall & ceiling painting

PANT-6F-02 Final internal painting

CARP-6F-01 Fixing of Door Frame

CARP-6F-02 Fixing of Door Shutter

CARP-6F-03 Fixing of Kitchen Cabinet

CARP-6F-04 Fixing of Wardrobes

MEP-6F-08 Bath Tub Fixing

MEP-6F-11 Sanitary fixing & Mixer

BLO-7F-01 cleaning

BLO-7F-02 Block layout and checking

BLO-7F-03 Block work -7F

BLO-7F-04 Internal Block Work

A0ON-7F-07 R.C.C Lintel

PLAS-7F-01 Wall Plaster - 7F

PLAS-7F-02 Celing Plaster- 7F

WRP-7F-02 Water proof coating to Wet areas

WRP-7F-03 Vertical side w/p of wet area

FLO-7F-11 Wet area -Ceramic Wall Clading

FLO-7F-06 Wet area- Ceramic flooring

FLO-7F-02 Floor Screed for Electrical Room

FLO-7F-01 Ceramic tile to entrance loby

FLO-7F-04 Skirting

FLO-7F-03 Ceramic tile iside the room

FLO-7F-05 Ceramic tiling to balconey and terrase

FLO-7F-08 Marble flooring to coridoor

FLO-7F-10 Corridor Wall Clading-Ceramic

FLO-7F-07 Telephone room & other room flooring

FLO-7F-09 Threshold

FAL-7F-01 7F-Balcony False Ceiling

FAL-7F-02 False Ceiling

PANT-7F-01 Internal wall & ceiling painting

PANT-7F-02 Final internal painting

CARP-7F-01 Fixing of Door Frame

CARP-7F-02 Fixing of Door Shutter

CARP-7F-03 Fixing of Kitchen Cabinet

CARP-7F-04 Fixing of Wardrobes

MEP-7F-08 Bath Tub Fixing

MEP-7F-12 Sanitary fixing & Mixer

BLO-HC-01 cleaning

BLO-HC-02 Block layout and checking

BLO-HC-04 Internal Block Work

BLO-HC-03 Block work -HC

A0ON-HC-10 R.C.C Lintel - HC

PLAS-HC-01 Wall Plaster - HC

A0AS-HC-02 Celing Plaster- HC

FLO-HC-07 rubber floor above screed in gym

FLO-HC-09 rubber skirting

FLO-HC-10 Graniti Ceramic tile( Steps to pool Dake Area)

FLO-HC-11 swimming pool wall clading

FLO-HC-14 Graniti Ceramic tile ( lift m/c room)

WRP-HC-02 Water proof coating to Wet areas

FLO-HC-02 White cement tiles

WRP-HC-03 Vertical side w/p of wet area

FLO-HC-04 wet area wall clading

FLO-HC-05 Ceramic flooring to swiming pool wall

A0LO-EX-02 Fixing of window sill

FLO-HC-01 Floor Screed for Electrical / store / tel room

FLO-HC-03 Marble flooring to lift loby

FLO-HC-06 Threshold

FLO-HC-08 Corridor Wall Clading-Ceramic

FLO-HC-12 Ceramic flooring to Filter Room

FLO-HC-13 Step to pool Deck

PANT-HC-01 Lift Int .wall bitumen coating

FAL-HC-01 False Ceiling

PANT-HC-02 Internal wall & ceiling painting

PANT-HC-03 Final internal painting

PANT-HC-04 Epoxy painting to staircase

CARP-HC-01 Fixing of Door Frame

CARP-HC-02 Fixing of Door shutter

MEP-HC-12 Sanitary fixing & Mixer

BLO-UR-01 Block work-UR

PLAS-UR-01 Wall Plaster- UR

PLAS-UR-02 Celing Plaster- UR

PLAS-UR-03 Staircase wall plaster

PLAS-UR-04 Staircase Ceilling plaster

CARP-UR-01 Fixing of Door Frame

CARP-UR-02 Fixing of Door shutter

MEP-B-02 MEP -Wall Conduites

MEP-B-03 Fixing of DB Back box ,GI box

MEP-B-04 Fixing of DB

MEP-B-06 Internal wiring

MEP-B-07 Main Cable work

MEP-B-08 Switches & Sockets

MEP-B-10 Instalation of Islolater for A/C

MEP-B-09 Light Fittings

MEP-GF-01 MEP -Wall Conduites

MEP-GF-02 Fixing of DB Back box ,GI box

MEP-GF-00 Fixing of DB

MEP-GF-04 Internal wiring

MEP-GF-06 Main Cable work

MEP-GF-08 Switches & Sockets

MEP-GF-10 Instalation of Islolater for A/C

MEP-GF-09 Light Fittings

MEP-1F-01 MEP -Wall Conduites

MEP-1F-04 Fixing of DB Back box ,GI box

MEP-1F-03 Fixing of DB

MEP-1F-05 Internal wiring

MEP-1F-07 Main Cable work

MEP-1F-10 Switches & Sockets

MEP-1F-12 Instalation of Islolater for A/C

MEP-1F-11 Light Fittings

MEP-2F-01 MEP -Wall Conduites

MEP-2F-02 Fixing of DB Back box ,GI box

MEP-2F-03 Fixing of DB

MEP-2F-05 Internal wiring

MEP-2F-07 Main Cable work

MEP-2F-10 Switches & Sockets

MEP-2F-12 Instalation of Islolater for A/C

MEP-2F-11 Light Fittings

MEP-3F-02 MEP -Wall Conduites

MEP-3F-04 Fixing of DB Back box ,GI box

MEP-3F-03 Fixing of DB

MEP-3F-05 Internal wiring

MEP-3F-07 Main Cable work

MEP-3F-10 Switches & Sockets

MEP-3F-12 Instalation of Islolater for A/C

MEP-3F-11 Light Fittings

MEP-4F-01 MEP -Wall Conduites

MEP-4F-04 Fixing of DB Back box ,GI box

MEP-4F-03 Fixing of DB

MEP-4F-05 Internal wiring

MEP-4F-07 Main Cable work

MEP-4F-10 Switches & Sockets

MEP-4F-15 Instalation of Islolater for A/C

MEP-4F-14 Light Fittings

MEP-5F-01 MEP -Wall Conduites

MEP-5F-04 Fixing of DB Back box ,GI box

MEP-5F-03 Fixing of DB

MEP-5F-05 Internal wiring

MEP-5F-07 Main Cable work

MEP-5F-13 Switches & Sockets

MEP-5F-15 Instalation of Islolater for A/C

MEP-5F-14 Light Fittings

MEP-6F-01 MEP -Wall Conduites

MEP-6F-03 Fixing of DB Back box ,GI box

MEP-6F-02 Fixing of DB

MEP-6F-06 Internal wiring

MEP-6F-07 Main Cable work

MEP-6F-13 Switches & Sockets

MEP-6F-15 Instalation of Islolater for A/C

MEP-6F-14 Light Fittings

MEP-7F-01 MEP -Wall Conduites

MEP-7F-03 Fixing of DB Back box ,GI box

MEP-7F-02 Fixing of DB

MEP-7F-05 Internal wiring

MEP-7F-07 Main Cable work

MEP-7F-13 Switches & Sockets

MEP-7F-14 Light Fittings

MEP-7F-15 Instalation of Islolater for A/C

MEP-HC-01 MEP -Wall Conduites

MEP-HC-02 Fixing of DB

MEP-HC-03 Fixing of DB Back box ,GI box

MEP-UR-01 MEP Wall Conduites & instalation of DB Box

MEP-HC-06 Internal wiring

MEP-HC-08 Main Cable work

MEP-HC-16 Switches & Sockets

MEP-HC-17 Light Fittings

MEP-HC-18 Instalation of Islolater for A/C

MEP-B-01 Water supply PEX piping

MEP-B-05 Water Supply PPR piping

MEP-GF-03 Water supply PEX piping

MEP-1F-02 Water supply PEX piping

MEP-GF-05 Water Supply PPR piping

MEP-2F-04 Water supply PEX piping

MEP-3F-01 Water supply PEX piping

MEP-1F-06 Water Supply PPR piping

MEP-2F-06 Water Supply PPR piping

MEP-4F-02 Water supply PEX piping

MEP-3F-06 Water Supply PPR piping

MEP-5F-02 Water supply PEX piping

MEP-4F-06 Water Supply PPR piping

MEP-6F-04 Water supply PEX piping

MEP-5F-06 Water Supply PPR piping

MEP-7F-04 Water supply PEX piping

MEP-6F-05 Water Supply PPR piping

MEP-HC-04 Water supply PEX piping

MEP-7F-06 Water Supply PPR piping

MEP-HC-05 Water Supply PPR piping

MEP-HC-07 Above ground Drainage

MEP-GF-11 Drainage Risers

MEP-GF-12 Water supply Riser

MEP-1F-13 Drainage Risers

MEP-1F-14 Water supply Riser

MEP-GF-15 Civil work for maanhole / fic /Sand traap /etc

MEP-2F-13 Drainage Risers

MEP-2F-14 Water supply Riser

MEP-3F-13 Drainage Risers

MEP-3F-14 Water supply Riser

MEP-GF-13 Water Heater fixing

MEP-4F-11 Drainage Risers

MEP-4F-12 Water supply Riser

MEP-1F-15 Water Heater fixing

MEP-2F-15 Water Heater fixing

MEP-5F-10 Drainage Risers

MEP-5F-11 Water supply Riser

MEP-3F-15 Water Heater fixing

MEP-6F-09 Drainage Risers

MEP-6F-10 Water supply Riser

MEP-4F-13 Water Heater fixing

MEP-7F-09 Drainage Risers

MEP-7F-10 Water supply Riser

MEP-5F-12 Water Heter fixing

MEP-HC-09 Water supply Riser

MEP-HC-10 Drainage Risers

MEP-6F-12 Water Heater fixing

MEP-HC-13 Roof water supply work

MEP-7F-11 Water Heter fixing

MEP-HC-11 Water Heter fixing

MEP-HC-14 Water tank Instlation

MEP-HC-15 Pump Fitting

A0VAC-B-17 Ducting work for A/C

A0AC-GF-17 A/C unit hanging (indoor)

A0AC-1F-18 A/C unit hanging (indoor)

A0VAC-B-19 Ref. piping Work

A0AC-GF-18 Ducting work for A/C

A0AC-GF-20 Ref. piping Work

A0AC-2F-18 A/C unit hanging (indoor)

A0AC-3F-18 A/C unit hanging (indoor)

A0AC-1F-19 Ducting work for A/C

A0AC-1F-21 Ref. piping Work

A0AC-2F-19 Ducting work for A/C

A0AC-4F-18 A/C unit hanging (indoor)

A0AC-2F-21 Ref. piping Work

A0AC-GF-19 Ext.Fan Fixing

A0AC-GF-21 Air out let fixing

A0AC-3F-19 Ducting work for A/C

A0VAC-B-16 Fresh air Duct

A0AC-3F-21 Ref. piping Work

A0AC-5F-18 A/C unit hanging (indoor)

A0VAC-B-18 Ext.Fan Fixing

A0VAC-B-20 Air out let fixing

A0AC-4F-19 Ducting work for A/C

A0AC-4F-21 Ref. piping Work

A0AC-6F-18 A/C unit hanging (indoor)

A0AC-2F-20 Ext.Fan Fixing

A0AC-2F-22 Air out let fixing

A0AC-1F-20 Ext.Fan Fixing

A0AC-1F-22 Air out let fixing

A0AC-5F-19 Ducting work for A/C

A0AC-7F-18 A/C unit hanging (indoor)

A0AC-3F-20 Ext.Fan Fixing

A0AC-3F-22 Air out let fixing

A0AC-6F-19 Ducting work for A/C

A0AC-5F-21 Ref. piping Work

A0AC-6F-21 Ref. piping Work

A0AC-4F-20 Ext.Fan Fixing

A0AC-4F-22 Air out let fixing

A0AC-HC-20 A/C unit hanging (indoor)

A0AC-7F-19 Ducting work for A/C

A0AC-7F-21 Ref. piping Work

A0AC-HC-21 Ducting work for A/C

A0AC-5F-20 Ext.Fan Fixing

A0AC-5F-22 Air out let fixing

A0AC-6F-20 Ext.Fan Fixing

A0AC-6F-22 Air out let fixing

A0AC-HC-24 Ref. piping Work

A0AC-HC-23 Ext.Fan Fixing

A0AC-HC-25 Air out let fixing

A0AC-7F-20 Ext.Fan Fixing

A0AC-7F-22 Air out let fixing

A0AC-HC-22 A/C units ( outdoor)

WPR-1F-01 Balcony W/P 1F

PAV-01 Precast Wheel Stopper

WPR-2F-01 Balcony W/P 2F

WPR-3F-01 Balcony W/P 3F

WPR-4F-01 Balcony W/P 4F

WRP-5F-01 Balcony W/P 5F

WRP-6F-01 Balcony W/P 6F

PLAS-EX-01 External roof area Plastering

WRP-7F-01 Balcony W/P 7F

PANT-EX-01 Epoxy painting to Roof

PLAS-EX-02 Airwell Plastering

PANT-EX-02 Epoxy painting to side of stair wall to S.Pool

MET-06 Balconey Rainling

PANT-EX-03 Fless Coat to Air Wall

WRP-HC-01 waterproofing to swiming pool

WRP-EX-01 Roof , Parapet wall W/P & Testing

WRP-EX-02 W/P to Air wall flr,skirt,R. rain water outlet

WRP-EX-03 Bitumen coating to External Block Wall -A

PLAS-EX-03 External elevation Plastering -A

FLO-EX-01 External elevation marble wall clading-A

MET-02 Aluminium Cladding On elevation- A

MET-04 Aluminium Claading Upper Roof Area

WRP-EX-04 Bitumen coating to External Block Wal- B

PLAS-EX-04 External elevation Plastering -B

FLO-EX-02 External elevation marble wall clading-B

MET-03 Aluminium Cladding On elevation- B

WRP-EX-05 Bitumen coating to External Block Wal-C

PLAS-EX-05 External elevation Plastering -C

FLO-EX-03 External elevation marble wall clading-C

MET-07 Aluminium Cladding On elevation- C

WRP-EX-06 Bitumen coating to External Block Wal-D

PLAS-EX-06 External elevation Plastering -D

FLO-EX-04 External elevation marble wall clading-D

MET-08 Aluminium Cladding On elevation- D

PAV-02 Fixing Kerb Stone at island & footh path

PAV-03 Fixing 60mm Paving block

PAV-04 80 mm Interlock at parking

PAV-05 Trafic line marking

A0MIS-03 Fixing of column guards

MET-05 Aluminium / door & Window

A0MIS-06 Compound Wall

MET-09 Staircase Hand Rail

MET-10 Cat ladders (For Airwel )

MET-11 Steel Pipe Gaurde (basement water side)

PR0-01 Security System

PR0-05 Gate barriers

PR0-03 Garbeg Disposal system

PR0-02 Pool Work

PRO-14 Reception counter

PR0-08 Instaltion Of Generator

PR0-09 TV system

PR0-06 Fixing of lockers

PR0-04 Sauna & Steam System

PR0-07 Lift instalation & Commissioning

PR0-11 Intercom system

PR0-10 Cradle system instalation

PR0-12 Transformar Instlation

PR0-13 Music system

TES-02 Testing & Commissioning

TES-01 Signage

TES-03 Civil Defance Inspection

TES-04 DM Inspection

TES-05 Complition certificate from DM

TES-06 P R O J E C T H A N D O V E R

SUCO-6F-15 Steel Work for 7.F Slab

SUCO-6F-16 MEP sleves & conduits for 7.F Slab

SUCO-6F-17 Seventh Floor Slab Casting (PART-B)

SUCO-6F-18 Deshuttering PART- B

SUCO-7F-01 steel work for column/A

SUCO-7F-02 Form work for column/A

SUCO-7F-03 Shear Wall /A

SUCO-7F-04 Column casting For RF /A Slab

SUCO-7F-05 Decking work for RF/A Slab

SUCO-7F-06 Steel Work for RF/A Slab

SUCO-7F-07 MEP sleves & conduits for RF/A Slab

SUCO-7F-08 Roof Floor Slab Casting[Part-A ]

SUCO-7F-09 Deshuttering PART- A

SUCO-7F-11 steel work for column

SUCO-7F-10 Shear Wall & Lift Core Wall

SUCO-7F-12 Form work for column

SUCO-7F-13 Column casting For RF Slab

SUCO-7F-14 Decking Work for R.F Slab

SUCO-7F-15 Steel Work for R.F Slab

SUCO-7F-16 MEP sleves & conduits for R.F Slab

SUCO-7F-17 Roof Slab Casting (PART-B)

SUCO-7F-18 Deshuttering PART- B

SUCO-HC-01 steel work for column

SUCO-HC-02 Shear Wall & Lift Core Wall

SUCO-HC-03 Form work for column

SUCO-HC-05 Parapet Wall

SUCO-HC-04 Column casting

SUCO-HC-07 Swimming pool Shell

SUCO-HC-10 Pool Deck

SUCO-HC-06 Decking Work for HC Slab

SUCO-HC-09 MEP sleves & conduits for HC Slab

SUCO-HC-08 Steel Work for HC Slab

SUCO-HC-11 Helth Club Slab Casting

SUCO-HC-12 Deshuttering

SUCO-UR-03 steel work for column

SUCO-UR-02 Shear Wall & Lift Core Wall

SUCO-UR-04 Form work for column

SUCO-UR-05 Parapet Wall above HC

SUCO-UR-01 Column casting For lift m/c room

SUCO-UR-06 Decking Work for lift m/c room

SUCO-UR-08 MEP sleves & conduits for lift m/c room

SUCO-UR-07 Steel Work for lift m/c room

SUCO-UR-09 Lift m/c room Slab

BLO-B-01 cleaning

BLO-B-02 Block layout and checking

BLO-B-03 Block work in Basement

BLO-B-04 R.C.C Lintel

PLAS-B-01 Wall Plaster - Basement

PLAS-B-02 Celing Plaster-Basement

FLO-B-02 marble flooring to lift loby

A0EXAV-09 Earth filling above raft 8’’tk

FLO-B-04 Marble Wall Clading to Lift Loby

FLO-B-05 4’’ PCC with mesh

FLO-B-07 Pump/ Store room flooring

FLO-B-01 Car parking /Driveway Floor Finishing

FLO-B-03 floor finish to water tank area

FLO-B-06 Wall clading to Pump room

FLO-B-08 Thrishold

FAL-B-01 False Ceiling

PANT-B-01 Internal wall & ceiling painting

PANT-B-02 Anticarbonation painting in wall

PANT-B-03 Final internal painting

CARP-B-01 Fixing of Door Frame

CARP-B-02 Fixing of Door Shutter

A0MIS-01 Substation Trenching Work

MET-01 Aluminium (LOUVER WORK) Substation

PANT-GF-01 Transformer room painting

A0PRO-17 Dewa Inspection Substation

A0PRO-18 Sub station hand over to DEWA

BLO-GF-01 cleaning

BLO-GF-02 Block layout and checking

BLO-GF-03 Internal Block Work

BLO-GF-04 Block work- GF

A0ON-GF-08 R.C.C Lintel

PLAS-GF-02 Celing Plaster- GF

PLAS-GF-01 Wall Plaster GF

WPR-GF-02 GF- Parking W/P

WPR-GF-01 Water proof coating to Wet areas

WPR-GF-03 Vertical side w/p of wet area

FLO-GF-08 Wet area wall clading ( garbage room)

FLO-GF-06 Wet area flooring (ceramic tiles)

WPR-GF-04 Water proofing to substation slab roof

FLO-GF-02 Floor Screed for Electrical Room/gym/

FLO-GF-01 4’’ PCC with mesh

FLO-GF-03 Floor Screed for M.hall

FLO-GF-05 Floor Screed for Electricaal Sub-station

FLO-GF-04 Car parking /Driveway Floor Finishing

FLO-GF-07 Floor Screed for Gym / Shop

FLO-GF-09 Mosaic flooring to stair floor & landing area

FLO-GF-10 Floor Screed for Gen. Room

FLO-GF-11 Store and other room flooring

FLO-GF-12 mosaic step

FLO-GF-14 Marble flooring to Entrance passage

FLO-GF-15 mosaic skirting for steps

FLO-GF-13 Threshold

FLO-GF-17 Fixing Marble Steps

FLO-GF-16 Marble Wall Clading to Lift Loby

FAL-GF-01 False Ceiling

PANT-GF-02 Internal wall & ceiling painting

PANT-GF-03 Final internal painting

PANT-GF-04 Anticarbonation painting in wall

CARP-GF-01 Fixing of Door Frame

CARP-GF-02 Fixing of Door Shutter

CARP-GF-03 Fixing of Kitchen Cabinet

CARP-GF-04 Fixing of Wardrobes

MEP-GF-07 Sanitary fixing & Mixer

BLO-1F-01 Cleaning

BLO-1F-02 Block layout and checking

BLO-1F-04 Block work- 1F

BLO-1F-03 Internal Block Work

A0ON-1F-07 R.C.C Lintel

PLAS-1F-02 Celing Plaster- 1F

PLAS-1F-01 Wall Plaster - 1F

WPR-1F-02 Water proof coating to Wet areas

WPR-1F-03 Vertical side w/p of wet area

FL0-1F-10 Wet area -Ceramic Wall Clading

FL0-1F-04 Wet area- Ceramic flooring

FL0-1F-02 Floor Screed for Electrical Room

FL0-1F-01 Ceramic flooring inside room

FL0-1F-03 Ceramic tiling to balconey and terrase

FL0-1F-05 Ceramic tile to entrance loby

FL0-1F-06 Marble flooring to Corridor

FL0-1F-07 Skirting

FL0-1F-09 Corridor Wall Clading-Ceramic

FL0-1F-08 Telephone room & other room flooring

FL0-1F-11 Threshold

FAL-1F-01 1F-Baalcony False Ceiling

FAL-1F-02 False Ceiling

PANT-1F-01 Internal wall & ceiling painting

PANT-1F-02 Final internal painting

CARP-1F-01 Fixing of Door Frame

CARP-1F-02 Fixing of Door Shutter

CARP-1F-03 Fixing of Kitchen Cabinet

CARP-1F-04 Fixing of Wardrobes

MEP-1F-08 Bath Tub Fixing

MEP-1F-09 Sanitary fixing & Mixer

BLO-2F-01 clening

BLO-2F-02 Block layout and checking

BLO-2F-04 Block work- 2F

BLO-2F-03 Internal Block Work

A0ON-2F-07 R.C.C Lintel

PLAS-2F-01 Wall Plaster - 2F

PLAS-2F-02 Celing Plaster- 2F

WPR-2F-02 Water proof coating to Wet areas

WPR-2F-03 Vertical side w/p of wet area

FLO-2F-10 Wet area -Ceramic Wall Clading

FLO-2F-05 Wet area- Ceramic flooring

FLO-2F-01 Ceramic tile to entrance loby

FLO-2F-02 Floor Screed for Electrical Room

FLO-2F-03 Ceramic tile iside the room

FLO-2F-04 Ceramic tiling to balconey and terrase

FLO-2F-06 Marble flooring to Corridor

FLO-2F-07 Skirting

FLO-2F-09 Corridor Wall Clading-Ceramic

FLO-2F-08 Telephone room & other room flooring

FLO-2F-11 Threshold

FAL-2F-01 2F-Baalcony False Ceiling

FAL-2F-02 False Ceiling

PANT-2F-01 Internal wall & ceiling painting

PANT-2F-02 Final internal painting

CARP-2F-01 Fixing of Door Frame

CARP-2F-02 Fixing of Door Shutter

CARP-2F-03 Fixing of Kitchen Cabinet

CARP-2F-04 Fixing of Wardrobes

MEP-2F-08 Bath Tub Fixing

MEP-2F-09 Sanitary fixing & Mixer

BLO-3F-01 cleaning

BLO-3F-02 Block layout and checking

BLO-3F-03 Block work -3F

BLO-3F-04 Internal Block Work

A0ON-3F-07 R.C.C Lintel

PLAS-3F-01 Wall Plaster - 3F

PLAS-3F-02 Celing Plaster- 3F

WPR-3F-02 Water proof coating to Wet areas

WPR-3F-03 Vertical side w/p of wet area

FLO-3F-08 Wet area -Ceramic Wall Clading

FLO-3F-03 Wet area- Ceramic flooring

FLO-3F-01 Ceramic tiling to balconey and terrase

FLO-3F-02 Ceramic tile iside the room

FLO-3F-06 Floor Screed for Electrical Room

FLO-3F-04 Ceramic tile to entrance loby

FLO-3F-05 Skirting

FLO-3F-07 Telephone room & other room flooring

FLO-3F-09 Marble flooring to Corridor

FLO-3F-10 Threshold

FLO-3F-11 Corridor Wall Clading-Ceramic

FAL-3F-01 3F-Baalcony False Ceiling

FAL-3F-02 False Ceiling

PANT-3F-01 Internal wall & ceiling painting

PANT-3F-02 Final internal painting

CARP-3F-01 Fixing of Door Frame

CARP-3F-02 Fixing of Door Shutter

CARP-3F-03 Fixing of Kitchen Cabinet

CARP-3F-04 Fixing of Wardrobes

MEP-3F-08 Bath Tub Fixing

MEP-3F-09 Sanitary fixing & Mixer

BLO-4F-01 cleaning

BLO-4F-02 Block layout and checking

BLO-4F-04 Block work -4F

BLO-4F-03 Internal Block Work

A0ON-4F-07 R.C.C Lintel

PLAS-4F-01 Wall Plaster - 4F

PLAS-4F-02 Celing Plaster- 4F

WPR-4F-02 Water proof coating to Wet areas

WPR-4F-03 Vertical side w/p of wet area

FLO-4F-09 Wet area -Ceramic Wall Clading

FLO-4F-08 Wet area- Ceramic flooring

FLO-4F-02 Floor Screed for Electrical Room

FLO-4F-01 Ceramic tile to entrance loby

FLO-4F-03 Ceramic tiling to balconey and terrase

FLO-4F-05 Marble flooring to Corridor

FLO-4F-04 Ceramic tile iside the room

FLO-4F-10 Telephone room & other room flooring

FLO-4F-06 Corridor Wall Clading-Ceramic

FLO-4F-07 Skirting

FLO-4F-11 Threshold

FAL-4F-01 4F-Balcony False Ceiling

FAL-4F-02 False Ceiling

PANT-4F-01 Internal wall & ceiling painting

PANT-4F-02 Final internal painting

CARP-4F-02 Fixing of Door Frame

CARP-4F-03 Fixing of Door Shutter

CARP-4F-01 Fixing of Kitchen Cabinet

CARP-4F-04 Fixing of Wardrobes

MEP-4F-08 Bath Tub Fixing

MEP-4F-09 Sanitary fixing & Mixer

BLO-5F-01 cleaning

BLO-5F-02 Block layout and checking

BLO-5F-04 Block work -5F

BLO-5F-03 Internal Block Work

A0ON-5F-07 R.C.C Lintel

PLAS-5F-01 Wall Plaster - 5F

PLAS-5F-02 Celing Plaster- 5F

WRP-5F-02 Water proof coating to Wet areas

WRP-5F-03 Vertical side w/p of wet area

FLO-5F-10 Wet area -Ceramic Wall Clading

FLO-5F-04 Wet area- Ceramic flooring

FLO-5F-01 Floor Screed for Electrical Room

FLO-5F-03 Ceramic tile to entrance loby

FLO-5F-06 Marble flooring to Corridor

FLO-5F-05 Ceramic tile iside the room

FLO-5F-02 Ceramic tiling to balconey and terrase

FLO-5F-08 Telephone room & other room flooring

FLO-5F-07 Corridor Wall Clading-Ceramic

FLO-5F-09 Skirting

FLO-5F-11 Threshold

FAL-5F-01 5F-Balcony False Ceiling

FAL-5F-02 False Ceiling

PANT-5F-01 Internal wall & ceiling painting

PANT-5F-02 Final internal painting

CARP-5F-02 Fixing of Door Frame

CARP-5F-03 Fixing of Door Shutter

CARP-5F-01 Fixing of Kitchen Cabinet

CARP-5F-04 Fixing of Wardrobes

MEP-5F-08 Bath Tub Fixing

MEP-5F-09 Sanitary fixing & Mixer

BLO-6F-01 cleaning

BLO-6F-02 Block layout and checking

BLO-6F-03 Block work -6F

BLO-6F-04 Internal Block Work

A0ON-6F-07 R.C.C Lintel

PLAS-6F-01 Wall Plaster - 6F

PLAS-6F-02 Celing Plaster- 6F

WRP-6F-02 Water proof coating to Wet areas

WRP-6F-03 Vertical side w/p of wet area

FLO-6F-11 Wet area -Ceramic Wall Clading

FLO-6F-05 Wet area- Ceramic flooring

FLO-6F-01 Floor Screed for Electrical Room

FLO-6F-03 Ceramic tile to entrance loby

FLO-6F-04 Ceramic tile iside the room

FLO-6F-02 Ceramic tiling to balconey and terrase

FLO-6F-06 Skirting

FLO-6F-09 Marble flooring to Corridor

FLO-6F-10 Corridor Wall Clading-Ceramic

FLO-6F-07 Telephone room & other room flooring

FLO-6F-08 Threshold

FAL-6F-01 6F-Balcony False Ceiling

FAL-6F-02 False Ceiling

PANT-6F-01 Internal wall & ceiling painting

PANT-6F-02 Final internal painting

CARP-6F-01 Fixing of Door Frame

CARP-6F-02 Fixing of Door Shutter

CARP-6F-03 Fixing of Kitchen Cabinet

CARP-6F-04 Fixing of Wardrobes

MEP-6F-08 Bath Tub Fixing

MEP-6F-11 Sanitary fixing & Mixer

BLO-7F-01 cleaning

BLO-7F-02 Block layout and checking

BLO-7F-03 Block work -7F

BLO-7F-04 Internal Block Work

A0ON-7F-07 R.C.C Lintel

PLAS-7F-01 Wall Plaster - 7F

PLAS-7F-02 Celing Plaster- 7F

WRP-7F-02 Water proof coating to Wet areas

WRP-7F-03 Vertical side w/p of wet area

FLO-7F-11 Wet area -Ceramic Wall Clading

FLO-7F-06 Wet area- Ceramic flooring

FLO-7F-02 Floor Screed for Electrical Room

FLO-7F-01 Ceramic tile to entrance loby

FLO-7F-04 Skirting

FLO-7F-03 Ceramic tile iside the room

FLO-7F-05 Ceramic tiling to balconey and terrase

FLO-7F-08 Marble flooring to coridoor

FLO-7F-10 Corridor Wall Clading-Ceramic

FLO-7F-07 Telephone room & other room flooring

FLO-7F-09 Threshold

FAL-7F-01 7F-Balcony False Ceiling

FAL-7F-02 False Ceiling

PANT-7F-01 Internal wall & ceiling painting

PANT-7F-02 Final internal painting

CARP-7F-01 Fixing of Door Frame

CARP-7F-02 Fixing of Door Shutter

CARP-7F-03 Fixing of Kitchen Cabinet

CARP-7F-04 Fixing of Wardrobes

MEP-7F-08 Bath Tub Fixing

MEP-7F-12 Sanitary fixing & Mixer

BLO-HC-01 cleaning

BLO-HC-02 Block layout and checking

BLO-HC-04 Internal Block Work

BLO-HC-03 Block work -HC

A0ON-HC-10 R.C.C Lintel - HC

PLAS-HC-01 Wall Plaster - HC

A0AS-HC-02 Celing Plaster- HC

FLO-HC-07 rubber floor above screed in gym

FLO-HC-09 rubber skirting

FLO-HC-10 Graniti Ceramic tile( Steps to pool Dake Area)

FLO-HC-11 swimming pool wall clading

FLO-HC-14 Graniti Ceramic tile ( lift m/c room)

WRP-HC-02 Water proof coating to Wet areas

FLO-HC-02 White cement tiles

WRP-HC-03 Vertical side w/p of wet area

FLO-HC-04 wet area wall clading

FLO-HC-05 Ceramic flooring to swiming pool wall

A0LO-EX-02 Fixing of window sill

FLO-HC-01 Floor Screed for Electrical / store / tel room

FLO-HC-03 Marble flooring to lift loby

FLO-HC-06 Threshold

FLO-HC-08 Corridor Wall Clading-Ceramic

FLO-HC-12 Ceramic flooring to Filter Room

FLO-HC-13 Step to pool Deck

PANT-HC-01 Lift Int .wall bitumen coating

FAL-HC-01 False Ceiling

PANT-HC-02 Internal wall & ceiling painting

PANT-HC-03 Final internal painting

PANT-HC-04 Epoxy painting to staircase

CARP-HC-01 Fixing of Door Frame

CARP-HC-02 Fixing of Door shutter

MEP-HC-12 Sanitary fixing & Mixer

BLO-UR-01 Block work-UR

PLAS-UR-01 Wall Plaster- UR

PLAS-UR-02 Celing Plaster- UR

PLAS-UR-03 Staircase wall plaster

PLAS-UR-04 Staircase Ceilling plaster

CARP-UR-01 Fixing of Door Frame

CARP-UR-02 Fixing of Door shutter

MEP-B-02 MEP -Wall Conduites

MEP-B-03 Fixing of DB Back box ,GI box

MEP-B-04 Fixing of DB

MEP-B-06 Internal wiring

MEP-B-07 Main Cable work

MEP-B-08 Switches & Sockets

MEP-B-10 Instalation of Islolater for A/C

MEP-B-09 Light Fittings

MEP-GF-01 MEP -Wall Conduites

MEP-GF-02 Fixing of DB Back box ,GI box

MEP-GF-00 Fixing of DB

MEP-GF-04 Internal wiring

MEP-GF-06 Main Cable work

MEP-GF-08 Switches & Sockets

MEP-GF-10 Instalation of Islolater for A/C

MEP-GF-09 Light Fittings

MEP-1F-01 MEP -Wall Conduites

MEP-1F-04 Fixing of DB Back box ,GI box

MEP-1F-03 Fixing of DB

MEP-1F-05 Internal wiring

MEP-1F-07 Main Cable work

MEP-1F-10 Switches & Sockets

MEP-1F-12 Instalation of Islolater for A/C

MEP-1F-11 Light Fittings

MEP-2F-01 MEP -Wall Conduites

MEP-2F-02 Fixing of DB Back box ,GI box

MEP-2F-03 Fixing of DB

MEP-2F-05 Internal wiring

MEP-2F-07 Main Cable work

MEP-2F-10 Switches & Sockets

MEP-2F-12 Instalation of Islolater for A/C

MEP-2F-11 Light Fittings

MEP-3F-02 MEP -Wall Conduites

MEP-3F-04 Fixing of DB Back box ,GI box

MEP-3F-03 Fixing of DB

MEP-3F-05 Internal wiring

MEP-3F-07 Main Cable work

MEP-3F-10 Switches & Sockets

MEP-3F-12 Instalation of Islolater for A/C

MEP-3F-11 Light Fittings

MEP-4F-01 MEP -Wall Conduites

MEP-4F-04 Fixing of DB Back box ,GI box

MEP-4F-03 Fixing of DB

MEP-4F-05 Internal wiring

MEP-4F-07 Main Cable work

MEP-4F-10 Switches & Sockets

MEP-4F-15 Instalation of Islolater for A/C

MEP-4F-14 Light Fittings

MEP-5F-01 MEP -Wall Conduites

MEP-5F-04 Fixing of DB Back box ,GI box

MEP-5F-03 Fixing of DB

MEP-5F-05 Internal wiring

MEP-5F-07 Main Cable work

MEP-5F-13 Switches & Sockets

MEP-5F-15 Instalation of Islolater for A/C

MEP-5F-14 Light Fittings

MEP-6F-01 MEP -Wall Conduites

MEP-6F-03 Fixing of DB Back box ,GI box

MEP-6F-02 Fixing of DB

MEP-6F-06 Internal wiring

MEP-6F-07 Main Cable work

MEP-6F-13 Switches & Sockets

MEP-6F-15 Instalation of Islolater for A/C

MEP-6F-14 Light Fittings

MEP-7F-01 MEP -Wall Conduites

MEP-7F-03 Fixing of DB Back box ,GI box

MEP-7F-02 Fixing of DB

MEP-7F-05 Internal wiring

MEP-7F-07 Main Cable work

MEP-7F-13 Switches & Sockets

MEP-7F-14 Light Fittings

MEP-7F-15 Instalation of Islolater for A/C

MEP-HC-01 MEP -Wall Conduites

MEP-HC-02 Fixing of DB

MEP-HC-03 Fixing of DB Back box ,GI box

MEP-UR-01 MEP Wall Conduites & instalation of DB Box

MEP-HC-06 Internal wiring

MEP-HC-08 Main Cable work

MEP-HC-16 Switches & Sockets

MEP-HC-17 Light Fittings

MEP-HC-18 Instalation of Islolater for A/C

MEP-B-01 Water supply PEX piping

MEP-B-05 Water Supply PPR piping

MEP-GF-03 Water supply PEX piping

MEP-1F-02 Water supply PEX piping

MEP-GF-05 Water Supply PPR piping

MEP-2F-04 Water supply PEX piping

MEP-3F-01 Water supply PEX piping

MEP-1F-06 Water Supply PPR piping

MEP-2F-06 Water Supply PPR piping

MEP-4F-02 Water supply PEX piping

MEP-3F-06 Water Supply PPR piping

MEP-5F-02 Water supply PEX piping

MEP-4F-06 Water Supply PPR piping

MEP-6F-04 Water supply PEX piping

MEP-5F-06 Water Supply PPR piping

MEP-7F-04 Water supply PEX piping

MEP-6F-05 Water Supply PPR piping

MEP-HC-04 Water supply PEX piping

MEP-7F-06 Water Supply PPR piping

MEP-HC-05 Water Supply PPR piping

MEP-HC-07 Above ground Drainage

MEP-GF-11 Drainage Risers

MEP-GF-12 Water supply Riser

MEP-1F-13 Drainage Risers

MEP-1F-14 Water supply Riser

MEP-GF-15 Civil work for maanhole / fic /Sand traap /etc

MEP-2F-13 Drainage Risers

MEP-2F-14 Water supply Riser

MEP-3F-13 Drainage Risers

MEP-3F-14 Water supply Riser

MEP-GF-13 Water Heater fixing

MEP-4F-11 Drainage Risers

MEP-4F-12 Water supply Riser

MEP-1F-15 Water Heater fixing

MEP-2F-15 Water Heater fixing

MEP-5F-10 Drainage Risers

MEP-5F-11 Water supply Riser

MEP-3F-15 Water Heater fixing

MEP-6F-09 Drainage Risers

MEP-6F-10 Water supply Riser

MEP-4F-13 Water Heater fixing

MEP-7F-09 Drainage Risers

MEP-7F-10 Water supply Riser

MEP-5F-12 Water Heter fixing

MEP-HC-09 Water supply Riser

MEP-HC-10 Drainage Risers

MEP-6F-12 Water Heater fixing

MEP-HC-13 Roof water supply work

MEP-7F-11 Water Heter fixing

MEP-HC-11 Water Heter fixing

MEP-HC-14 Water tank Instlation

MEP-HC-15 Pump Fitting

A0VAC-B-17 Ducting work for A/C

A0AC-GF-17 A/C unit hanging (indoor)

A0AC-1F-18 A/C unit hanging (indoor)

A0VAC-B-19 Ref. piping Work

A0AC-GF-18 Ducting work for A/C

A0AC-GF-20 Ref. piping Work

A0AC-2F-18 A/C unit hanging (indoor)

A0AC-3F-18 A/C unit hanging (indoor)

A0AC-1F-19 Ducting work for A/C

A0AC-1F-21 Ref. piping Work

A0AC-2F-19 Ducting work for A/C

A0AC-4F-18 A/C unit hanging (indoor)

A0AC-2F-21 Ref. piping Work

A0AC-GF-19 Ext.Fan Fixing

A0AC-GF-21 Air out let fixing

A0AC-3F-19 Ducting work for A/C

A0VAC-B-16 Fresh air Duct

A0AC-3F-21 Ref. piping Work

A0AC-5F-18 A/C unit hanging (indoor)

A0VAC-B-18 Ext.Fan Fixing

A0VAC-B-20 Air out let fixing

A0AC-4F-19 Ducting work for A/C

A0AC-4F-21 Ref. piping Work

A0AC-6F-18 A/C unit hanging (indoor)

A0AC-2F-20 Ext.Fan Fixing

A0AC-2F-22 Air out let fixing

A0AC-1F-20 Ext.Fan Fixing

A0AC-1F-22 Air out let fixing

A0AC-5F-19 Ducting work for A/C

A0AC-7F-18 A/C unit hanging (indoor)

A0AC-3F-20 Ext.Fan Fixing

A0AC-3F-22 Air out let fixing

A0AC-6F-19 Ducting work for A/C

A0AC-5F-21 Ref. piping Work

A0AC-6F-21 Ref. piping Work

A0AC-4F-20 Ext.Fan Fixing

A0AC-4F-22 Air out let fixing

A0AC-HC-20 A/C unit hanging (indoor)

A0AC-7F-19 Ducting work for A/C

A0AC-7F-21 Ref. piping Work

A0AC-HC-21 Ducting work for A/C

A0AC-5F-20 Ext.Fan Fixing

A0AC-5F-22 Air out let fixing

A0AC-6F-20 Ext.Fan Fixing

A0AC-6F-22 Air out let fixing

A0AC-HC-24 Ref. piping Work

A0AC-HC-23 Ext.Fan Fixing

A0AC-HC-25 Air out let fixing

A0AC-7F-20 Ext.Fan Fixing

A0AC-7F-22 Air out let fixing

A0AC-HC-22 A/C units ( outdoor)

WPR-1F-01 Balcony W/P 1F

PAV-01 Precast Wheel Stopper

WPR-2F-01 Balcony W/P 2F

WPR-3F-01 Balcony W/P 3F

WPR-4F-01 Balcony W/P 4F

WRP-5F-01 Balcony W/P 5F

WRP-6F-01 Balcony W/P 6F

PLAS-EX-01 External roof area Plastering

WRP-7F-01 Balcony W/P 7F

PANT-EX-01 Epoxy painting to Roof

PLAS-EX-02 Airwell Plastering

PANT-EX-02 Epoxy painting to side of stair wall to S.Pool

MET-06 Balconey Rainling

PANT-EX-03 Fless Coat to Air Wall

WRP-HC-01 waterproofing to swiming pool

WRP-EX-01 Roof , Parapet wall W/P & Testing

WRP-EX-02 W/P to Air wall flr,skirt,R. rain water outlet

WRP-EX-03 Bitumen coating to External Block Wall -A

PLAS-EX-03 External elevation Plastering -A

FLO-EX-01 External elevation marble wall clading-A

MET-02 Aluminium Cladding On elevation- A

MET-04 Aluminium Claading Upper Roof Area

WRP-EX-04 Bitumen coating to External Block Wal- B

PLAS-EX-04 External elevation Plastering -B

FLO-EX-02 External elevation marble wall clading-B

MET-03 Aluminium Cladding On elevation- B

WRP-EX-05 Bitumen coating to External Block Wal-C

PLAS-EX-05 External elevation Plastering -C

FLO-EX-03 External elevation marble wall clading-C

MET-07 Aluminium Cladding On elevation- C

WRP-EX-06 Bitumen coating to External Block Wal-D

PLAS-EX-06 External elevation Plastering -D

FLO-EX-04 External elevation marble wall clading-D

MET-08 Aluminium Cladding On elevation- D

PAV-02 Fixing Kerb Stone at island & footh path

PAV-03 Fixing 60mm Paving block

PAV-04 80 mm Interlock at parking

PAV-05 Trafic line marking

A0MIS-03 Fixing of column guards

MET-05 Aluminium / door & Window

A0MIS-06 Compound Wall

MET-09 Staircase Hand Rail

MET-10 Cat ladders (For Airwel )

MET-11 Steel Pipe Gaurde (basement water side)

PR0-01 Security System

PR0-05 Gate barriers

PR0-03 Garbeg Disposal system

PR0-02 Pool Work

PRO-14 Reception counter

PR0-08 Instaltion Of Generator

PR0-09 TV system

PR0-06 Fixing of lockers

PR0-04 Sauna & Steam System

PR0-07 Lift instalation & Commissioning

PR0-11 Intercom system

PR0-10 Cradle system instalation

PR0-12 Transformar Instlation

PR0-13 Music system

TES-02 Testing & Commissioning

TES-01 Signage

TES-03 Civil Defance Inspection

TES-04 DM Inspection

TES-05 Complition certificate from DM

TES-06 P R O J E C T H A N D O V E R

Member for

20 years 4 months

Hi all,

Hi Mr Khaled

Hi Mr Sukumaran Subaramaniyan



I intend to set some kind of rewarding system as a motivation for our selves to work on this project.

So, I need to formulate an evaluation committee to evaluate posts then based on the committee evaluation the Planner will win the reward for each approved post.



-----------

The Reward:

-----------

All participants that their posts are approved by the committee will win a valuable Project Management Book and have the right to select one of the following books:

- McGraw Hill - Project Management

- Mcgraw-Hill The Six Sigma Project Planner Ebook

- AMACON - Modern Project Management

- Project Management - New Six Sigma - A Leader Guide To Achieving Rapid Business (Prentice Hall)

- Project Management - The Evolutionary Project Manager’s Handbook

- Project Management - The Project Manager’s MBA

- Project Management Manual

- Project Management Skills

- Project Manager Manual

- Wiley - Practical Project Management

- Wiley - Project Management Methodologies



So, Mr Khaled,Mr Sukumaran Subaramaniyan I invite you to be the first two members of the A/M committee so, please if you agree let me know.



All members can begin posts submition and receiving rewards from now. temporarily I will evaluate the posts till the committee is founded and any one of the members is encouraged to sent his evaluation to any post.



Thank You all,



Hussein Abdel Maksoud, M.Sc. construction Management

hamaksoud@yahoo.com

Member for

24 years

Hi Hussein,



As a begining stop dividing the subject and copying it to another Posts. i understand that u want to differentiate between different trades but this will not help.



What really help is that u atleast start with one trade then once its finished u can start the other ones, where u will find that 60% of information for the next trade was discussed, because trades sequence is like a net.



So just start with one trade if i m not mistaken Start with Construction and leave the Pre-Construction(MasterPlan, Design & Engineering,Tendering)to a later stage.



as u have categorized yr Method Statement lets start on:



1- List of activities including prerequisits.



Civil & Infrastructure Works for Terrestrial(Marine Works will Need another Category):



- Mobilization

- Enabling Works

- Enviromental Remediation Works

- Land Reclamination & Mass Grading

- Infrastructure Works

- Building Structure

(Lets Start listing activities for the above ones, as u know they can be built from a huge number of activities, this was a start-up)



as for the hereunder catergories lets add ther comments also.



2- Activity Sequence (either mandatory or discretionary).

3- Resources required (including material, labor, equipment).

4- Factors to be considered for duration estimation.

5- Lags or leads that may be required.

6- Risk factors in metrics of cost and time impact.





Its a huge job it need patient and time, but its a startup.



regards,


Member for

20 years 4 months

Dear Mr. Khaled Bashiti, Dear All,



Thank you very much on your response in our brainstorming.



1. You are right, the subject needs to be more simplified and clear with definite form and deliverables and I am working on that.



2. The WBS I suggested depended on the Idea of standardization not on specific type of structure, location,.... the output we hope to get out of this brainstorming is a categorized list of all workpackages that a planning engineer may face in any project with the method of construction of each. When the planner works on a real world project he will select only packages included in his project and put them in the appropriate location in his project WBS.



If we considered your example:



1. The realworld project will be an Hotel with the following potion of a WBS:



+ Hotel Project

+ Basement

....

+ Ground floor

....

+ Firtst floor

+ Main Corridor,Lift Looby,Room Enterance

....

+ Rooms

....

+ Toilets

- MEP works

- Finishes

- Fit-outs

- Furnitures

+ Service Rooms

....



2. Deliverables in our project will be organized in a standardized fashion not in a projectized fashion to include all possible types of work under each category (Uniformat) as shown totally in my topic "Methods of Construction" on this forum.



for example: the Planner in the realworld project (the above shown WBS) needs the MEP, Finishes, Fit-outs and Furnitures not only once but several times according to instances of occurance on the project but he will find each one in only one location in out "project for standardization" he will find:



- MEP in Item D of the Uniformat (shown in my topic "Methods of Construction")



- Equipment in Item E of the Uniformat (shown in my topic "Methods of Construction")



- Finishes and fit-outs in Item C of the Uniformat (shown in my topic "Methods of Construction")



and so on.



3. The planner takes all his packages and palce them where ever needed in his realworld project.



-----------------------------------------------------------



The question now is "What do we mean exactly with Method of construction?"



Well, The initial meaning I suggest to start with is (According to PMI-PMBOK 2000):

- List of activities including prerequisits.

- Activity Sequence (either mandatory or discretionary).

- Resources required (including material, labor, equipment).

- Factors to be considered for duration estimation.

- Lags or leads that may be required.

- Risk factors in metrics of cost and time impact.



Mr. Khaled Thanks a lot and I hope to receive more of your responses and ideas to help in completing this project.



Thank you All,



Hussein Abdel Maksoud, MSc Construction Management.

hamaksoud@yahoo.com

Member for

24 years

Hi Hussein,



unfortunetly the way u r presenting the issue confuse the viewers, if u want to do a method statement for Interior works or for Furniture or MEP or Structure you can’t just come and list Codes.



Simply say i need to get information concerning this subject whats the best way to deal with.



Answers will fly over from all memebers.



to push members to participate u should guide them with a startup



Example:



Method statement for Interiors u have to differntiate between Finishes, Fit-outs & Furnitures & Equipments.



Usually what can we say is the best way to proceed with work in a Hotel(specify the project because u have a large scale of jobs)even which part of a Hotel Typical Floors



how u will do the Works simply we will break Each Level of the Typical Floors into Zones(1- Main Corridor, Lift Looby, & Room Enterance all Togather. 2- Rooms. 3- Toilets. 4- Service Rooms) this break down it depends upon the included trades means: each zone have its own MEP works also Finishes, Fit-outs, & Furnitures automatically the crews can be divided into those zones.



So We have to Specify the 1- Project Type 2- Trade 3- Zone

4- Gangs Flow



Depending at Project type each one can put his input, also according to Trade.



hope that i have helped without any misunderstanding.

regards,