Hi All,
I am facing problem in getting correct variance - BL project finish date in P6. My assigned program has project finish date of 09-Jun-23 and my current update program has project finish date of 09-Aug-23 whereas i am getting 53 days in the column of variance - BL project finish date in P6 instead of 61 days kindly guide and advise how to rectify it.
Regards