I am using Duration Type of Fixed Units for some activities. The Units are from the Cost Estimate. When I allocate a Resource to the Activity, the Duration changes accordingly to match the Resource Availability (12h/D).
So an activity with 120 hours as Units generates a Duration of 10 days when the Resource is assigned.
But when I add a second Resource ( the same Resource now on the activity twice), the Units double and the duration remains the same.
Which is exactly the opposite of what should happen, Units should remain at 120 hours and the Duration should shrink to 5 days.
Any ideas what I am doing wrong?