Morning all, I've got an activity whose predecessor has completed but in the predecessor tab it says 'lag finish' and it several days later pushing out a date artificially. I can't seem to find any explanation as to how this is calculated. Screen shot below of a similar item. I've checked all preceeding activities and there are none outstanding and none suggesting the date as 6th March.
Thanks in advance for any assistance.
EDIT - found the issue kinda, so the activity above completed on the 3rd the data date is the 5th and that is what pushed my activity out to the 7th, I don't understand why it couldn't start on the 6th.