Hi,
Contractor's schedule is loaded with manhours for the progress measurement. Due to significant delays, recovery program is being developed with additional resources, means additional manhours to meet the agreed target date.
Is it ok to add additional manhours to activities to show the recovery action, but this will affect the total manhours and accordingly the progress values already reported. or is it enough to explain the recovery actions in the narrative and keeping the original manhours as it is, without affecting the progress measurement.
Please share any input.