April 29 Data Date
April 29 Actual start on activity
Orig Dur = 20
Actual Dur = 5
Rem. Dur = 20
Per. Complete Type = Dur.
Dur. Complete = 0%
Sched. % Complete = 45% - how is this possible.
float -39.
Should I tell the contractor it has to be wrong to have used 5 days because the actual is on the data dates so cold not have used 5 days but a bigger question is how can the Sched % complete show 45% -seems high to me, I do not understand it.