For those of you that deal with the Schedule of Values vs CPM schedule connection: I have been on project where the CM/owners leave items at 99% to make sure punchlist items are corrected...- that skews the schedule when items are essentially 100% complete but have to leave at 99%. Do you always have Punchlist Item on the SOV? Any SOV tips for easy comparison to the CPM? (or submittal logs which is a can of worms vs schedule)