So to calc a completion date in excel that includes the NTP date itself is @sum((A1+A2)-1) because excel does not count the NTP date in that formula. With a A1 being the NTP date and A2 being that Calendar Days. Are there any other, or different formulas you use to quickly calc dates in excel. (I see date off by 1 all the time.)