Hi, I've just created a new baseline, a mid-project baseline on a project to track from now and till end of project. But I experience that the new baseline is not synced with the period actual earned value as I would expect.
Why does Primavera not do the calculation based on remaining unit value, and mirror the history? Is there a applicaton setting that I have missed out?
Here is an example from 1 of the activities. I would expect that the baseline before the datadate would be equal to the orange earned value, and to the right of the datadate would continue from where the orange earned value ends on the datadate.