Hi Everyone,
I have an activity (as shown in the screen shot below) which will not allow me to reset the Remaining Duration or Atr Complete Duration or force an Expected Finish Date because of the message 'Remain Finish Date cannot be earlier than Remain Start Date'.
I am guessing this is talking about the Late Finish Date or maybe the Planned Finish Date? either way, the reduced duration that I want to enter is not accepted, the Expected Finish Date that I want is Correct, so how do I clear the fields that are generating this message? I have removed all predecessors and successors, rescheduled, refresshed but still can not get past this limitation.