Hi Pplanners and PP users,
When I export a PP project as an XER file, the Currency thousand separator field remains empty; as a result, P6 does not want to import the project; I have to open the XER file in MS Excel, fill in the field and so on.
I have not found yet where to set up the thousand separator in Powerproject, it would help a lot.
By the way, many thanks to Malcolm Emmerson for his webinar earlier this week, very good!
Alexandre