In a schedule with a structured WBS what is the best practice for the activity names - example
WBS: Site1/Building5/Area3/Machine foundations/
Activity Name: Pour Concrete
OR: Activity Name: Pour Machine foundation concrete at Site1, Building5, Area3
Duplicated info but using layouts without the WBS structure, "Pour Concrete" isnt helpful.
Is there an accepted best practice.
Thanks