Hello all,
My site was shutdown on the 24-Mar-20 due to Corona virus.
However, my subcontractors returned to site at different time.
Some of them returned on 15-Jun-20, some returned on 29-Jun-20, some on 22-Jun-20 and some on 03-Aug-20.
My commercial team want to see the bars discontinue at these dates for different subcontractors. I have applied all the different calenders to each subcontractors.
How do i show the splitted between those actities?
For example. if the activity started the works on 01-Feb-20 but stopped on 24-Mar-20 and resumed on 15-Jun-20. How do i show the period between 24-Mar & 14-Jun-20 as blanked? (i have applied calender)