Hello Again!
I have another P6 question......We have set up a filter for 2 week look ahead and it works. However, instead of using the high value of DD+2W, we changed it to DD +13d (due to projects having different data dates). The problem is, we are not getting all the activities - example, if our filter for 13 days went to Oct 1 from the data date, we are only getting up to Sep 29. My question is - does P6 calculate differently when using weeks instead of days?