A doubt. I have received comments on a schedule,
- The use of Finish-start relationship is prefered (FS). Avoid as much possibe use of Finish-Finish (FF) plus lags and start -start (SS) plus lags relationship between activities.
- FF relationship do not provide visiblity and clarity regarding schedule logics and drivers fr key activity.
Is the above statement right ?
Moreover in my schedule I have no open end activity, each activity will either have FF or FS or SS relationship with a lag. So would ac activity be considred "Opend End" if it the predecedosr/sucessor rlationship is having only FF or SS ?
Is only FS relation is considred as Closed end ?