Hello I have two issues:
1. When exporting an Excel to add resources and costs - I need to add add multiple resources or cost values for one activity - I cant get a worksheet that gives me a row per resource. Is this possible?
2. Where I have resources e.g. say Install Concrete has Units 100, if actual units are 45 (45% complete); then why wouldn't remaining units be 55? How is this supposed to calculate.
Thanks