Hi,
I have a calendar running 10 hours per day, 5 days per week. It is assigned as the Activity default calendar. When I create a new activity with a duration of 3 days and then change my User Preference to show Duration in Hours, the hours are only 24 but I expected them to be 30.
Why is this happenning? 3 days on a 10 hour per day calendar should be 30 hours but it appears to be referencing an 8 hour day.
You help would be greatly appreciated.
Rod