Please explain if a project has Cost Variance of 6.93% and Baseline Duration of 486 days how can we calculate the Delay days based on Early % Variance.Can somebody explain
If Planned 16.14%
Actual 9.21%
Cost Variance - 6.93%
Please explain if a project has Cost Variance of 6.93% and Baseline Duration of 486 days how can we calculate the Delay days based on Early % Variance.Can somebody explain
If Planned 16.14%
Actual 9.21%
Cost Variance - 6.93%
Links:
[1] http://www.planningplanet.com/forums/oracle-primavera-pm6