I'm hoping someone can help me. I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.
Can anyone help?
I'm hoping someone can help me. I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.
Can anyone help?