P6 Filter

2 replies [Last post]
Heather Hadley
User offline. Last seen 2 weeks 5 hours ago. Offline
Joined: 29 Jan 2019
Posts: 15
Groups: None

I'm hoping someone can help me.  I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.

 

Can anyone help?

Replies

Heather Hadley
User offline. Last seen 2 weeks 5 hours ago. Offline
Joined: 29 Jan 2019
Posts: 15
Groups: None

Thanks!!

Santosh Bhat
User offline. Last seen 11 hours 39 min ago. Offline
Joined: 15 Apr 2005
Posts: 260

Heather,

Use the top row of a filter to change the statement from "all" to "any" and then you can have three rows like this

Row 1) Finish is less than DD+2w (if you want two weeks from the data date, CD+2w if you want from the current date)

OR

Row 2) Activity Type = Start Milestone

OR

Row 3) Activity Type = Finish Milestone