Hi all,
I am a frustrated P6 V18 user and have an intiguing issue at the moment. In one of my programs which I inherited from another planner I have an activity doing something very strange. Activities were loaded with resources reflecting the revenue/claim value for the project for the activity. Some of these involve LOEs for indirects. In one of these activities the Remaining Units/Time and thus the Remaining Units double every time I choose to reschedule leading to an exponential error. There is nothing particularly uniique about this activity as there are others like it in the program that are not behaving like this. Has anybody else had an issue like this?