After series of delays in the project that i'v been working on, the client ask for a re-baseline of the planning. I'm wondering if i could re-baseline with actual progress and submit it as the new baseline of the project. Or, should i remove all actual progress and start all over to match actual dates and then submit it clear of any progress.
Thanks,