Hello Everyone,
May be this topic has been dicussed here but couldnt find it.
The situation is I am the Client Planning Engineer for a "Building Project". I have 2 Subcontractors Civil Contractor and MEP Contractor and they have prepared the baseline schedule.
So I need to update my schedule which is a combination of Civil and MEP Works. So I want to import data from Civil Contractors updated scheule as well as MEP Contractors updated schedule.
At the end I have one updated schedule which shows both Civil and MEP Work.
How Is this done ?
Any link or a pictorial represntation on how to do that would be really helpful.
Regards
Jithin