I have an EPC schedule that has been manhours and resourced loaded to the baseline. However, I have already actualized activies and I have also delelted some activites as well per PM. Now the PM is telling me I need to reduce the amount of manhours. What would be the best solution going forward? Would i need to revert the baseline, adjust the manhours and then convert it back? Or do I maintain the current data date baseline, adjust the manhours and then assign as the new baseline? Any input helps. thanks.