Hi,
When an activity is Started and a Physical % applied (eg 80%), I F9, and the Actual Labor Units remain at zero.
When I look in the Resources tab of the Activity Details window the Units % Complete is also zero. If I manually adjust the Units % Complete the Actual Labor Units then adjust correctly.
My settings are:
Act Type: Task Dependent
Dur Type: Fixed Duration & Units
% Complete Type: Physical
What other settings would be likely tyo be causing this problem?
Thanks very much
Dave