I am receiving an xer for the schedule update from the Contractor. The percent complete used for progress is the Cost Percent Complete. However, when I inserted the baseline into the schedule, the values on the Cost Percent Complete changes. When i removed the baseline, the Cost Percent Complete return to its original values. Does anyone knows the reason behind this? Thanks