Good morningPlease am having issues when reporting, when ever i have to update the percentage work progress in it changes the finished date assigned to it by reducing the actual date and if i try to bring it back to the actual date that is assigned to it, it will reduce the percentage to zero percent. what is cause am confused in P6 Thanks