I am fairly new to Primavera, therefore the below question may seem a little strange to some of the pros here.
In the programme update for the client, I've been asked by a colleague to calcualte % complete that we should be on as of Data Date used for the current reporting period. I normally use % Schedule Complete to show the % complete that we should be on now. (I hope this is the right way of doing it!)
If this is the correct way of identify the % Complete we should be as of a specific Data Date, then which Baseline would this be calculated against - Project BL, Primary BL..etc? What if I have few BL assiged, which one will be picked up?
I apprecate your help!
Katia