As per the following below Resource Curve and for an activity of 20 Days Original Duration the Planned Value will be exactly located on last day of the activity.
But for any activity with Original Duration more than 20 Days, the Planned Value will not be located in the last day of the activity.
Please advise how we can get the planned Value exactly on the last day of the activity for those activities exceed 20 Days original duration.